Property buyers alert: Verify carpet area on UPRERA portal and don’t buy apartment on the basis of super area, advises UPRERA AuthorityUP RERA is strongly advising homebuyers to purchase properties based on carpet area, not super built-up area. This ensures buyers pay only ...
12 Jun, 2026, 10.43 AM IST
Homeowner having possession must pay maintenance charges even if builder did not give OC, independent water connection and sewerage facilities, rules HP RERAHomeowners in possession must pay maintenance charges even without an Occupation Certificate or independent water and sewerage facilities. ...
01 Jun, 2026, 07.11 AM IST
Builder delayed possession and charged Rs 75 lakh extra on the basis of super area instead of carpet area; homebuyers partly win case in Punjab RERA for delayed possessionHomebuyers in Amritsar received partial victory from Punjab RERA regarding delayed possession. The authority ordered the builder to pay int...
30 May, 2026, 04.42 PM IST
Big win for homebuyers after 10-year wait: Haryana RERA directs Gurugram-based builder to pay 10.80% interestHRERA, in its April 7 order, ruled in favour of two allottees who had lodged a complaint against M/s KNS Infracon Pvt Ltd and its associate...
29 Apr, 2026, 04.04 PM IST
Bombay HC upholds homebuyers' right to withdraw builder's deposit during appeal; How will this speed up refund on delayed projects?In a significant ruling for the real estate sector, the Bombay High Court has affirmed that homebuyers can withdraw amounts deposited by bu...
02 Apr, 2026, 11.31 AM IST
MPs panel to push central check on RERA bye-laws: Housing minister Manohar Lal KhattarHousing Minister Manohar Lal Khattar announced that a parliamentary committee will urge states to have central teams vet RERA bye-laws befo...
16 Feb, 2026, 12.37 AM IST
Flat ready but keys not handed over: Karnataka RERA rules landowner are promoters too, orders Rs 6 lakh payout to homebuyers for delayed possessionKarnataka RERA has ruled that landowners are also considered promoters under the RERA Act. This decision came after homebuyers filed a case...
12 Dec, 2025, 11.06 AM IST
Bengaluru homebuyer wins Rs 29 lakh and interest compensation after builder delays flat possession by nearly 4 yearsA Bengaluru homebuyer has won a significant victory against a builder. After a lengthy delay in getting possession of their apartment, the ...
19 Nov, 2025, 04.17 PM IST
Homebuyer to get Rs 1.28 crore refund with interest as MahaRERA raps builder for prolonged delay in getting OCA homebuyer will receive a Rs 1.28 crore refund with interest from a builder. MahaRERA ordered the payment after the project failed to get ...
15 Nov, 2025, 12.44 PM IST
Possession delay: MahaREAT asked homebuyer to pay Rs 13 lakh interest to builder despite 2.5 years delay in delivery of Rs 1.65 crore apartmentA Mumbai homebuyer will pay Rs 13 lakh net interest to a builder after deduction of his interest payment from the builder. The builder must...
07 Nov, 2025, 02.56 PM IST
Homebuyers win MahaREAT case despite unregistered sale agreement; to get Rs 23 lakh with interest from builders for delay in possessionThe Maharashtra Real Estate Appellate Tribunal ruled that builders cannot use unregistered sale agreements as an excuse for delays. Homebuy...
06 Nov, 2025, 12.37 PM IST
Delhi NCR builder ordered to pay Rs 85 lakh for delayed home possession: Haryana RERA judgment explainedHaryana RERA has ordered a prominent builder to pay Rs 85 lakh in interest compensation to the Batra family for a five-year delay in handin...
11 Oct, 2025, 09.59 AM IST
Bengaluru homebuyer to get Rs 70 lakh from builder due to three year delay in possession; Know how RERA law helped him win the caseA Bengaluru homebuyer secured a victory against a builder in the Karnataka RERA tribunal. The builder failed to complete the apartment proj...
28 Aug, 2025, 11.20 AM IST
RERA Impact: Builder asked to pay Rs 2.56 crore compensation and foreclose homebuyer’s housing loan due to 7-year delay in possession of flatRERA: A homebuyer who took home loan to buy an apartment in Bengaluru faced challenges when the bank started charging the EMIs but construc...
21 Apr, 2025, 02.19 PM IST
RERA is coming up short in giving relief to homebuyers. What ails the legislation?According to data from the Ministry of Housing and Urban Affairs, RERA authorities across states have disposed of 82,750 complaints since t...
31 Jan, 2022, 06.30 AM IST
Construction work on stuck Knight Court project of Jaypee Greens resumesKnight Court is among the five projects at Wish Town that are promoted, sold, and developed by JAL, not Jaypee Infratech Ltd, which is in i...
22 Feb, 2021, 06.01 PM IST
Centre issues advisory to states to extend deadline for completion of real estate projectsIn a statement, the Union Housing and Urban Affairs Ministry said the measure will safeguard the interest of homebuyers, who will get the d...
13 May, 2020, 10.23 PM IST