Big win for homebuyers after 10-year wait: Haryana RERA directs Gurugram-based builder to pay 10.80% interest
HRERA, in its April 7 order, ruled in favour of two allottees who had lodged a complaint against M/s KNS Infracon Pvt Ltd and its associate developer in the Capital Gateway project. They had booked a 2,675 sq ft flat each, paid over Rs 1.8 crore.

This is the story of several buyers who booked their flats in Capital Gateway housing project in Gurugram’s Sector 111, which has faced long delays. Several homebuyers of the project even held a protest at the project site in December last year, urging Haryana Real Estate Regulatory Authority (HRERA) to review the approvals, have time-bound hearings and ensure strict enforcement of provisions.
Now, two buyers, who have been waiting to get the possession of their unit for over a decade now despite paying Rs 1.8 crore for the booking, have finally received some relief from HRERA, which has directed the builder to pay 10.8% annual interest for the delay in handing over possession.
ALSO READ | Big relief for homebuyers: UP RERA caps builder fees on these flat transfers, know how it will apply
Capital Gateway housing project delay: Relief for homebuyers
HRERA, in its April 7 order, ruled in favour of two allottees who had lodged a complaint against M/s KNS Infracon Pvt Ltd and its associate developer in the Capital Gateway project. They had booked a 2,675 sq ft flat each, paid over Rs 1.8 crore. However, the builder “unilaterally and unauthorizedly” increased the super area of the booked dwelling unit by 315 sq ft and demanded Rs14,40,809.
In their complaint, the buyers mentioned that they “came to know about the fact that the respondents had no intention to deliver the project and was dragging their feet by indulging into delaying and dilatory tactics unfairly to fleece the complainant not caring for completing the project in promised time span.”
As per the builder buyer agreement dated February 11, 2015, the project was to be completed within 36 months from the date of sanction of the building plans of the said residential project. The complaint stated that due date of delivery of possession to be June 7, 2015.
In its order, HRERA noted that the respondents (builders) failed to file a reply or even appear before it despite notices to them. On the basis of the material on record, the authority held that the developer had violated Section 11(4)(a) of the Rera Act, which requires promoters to complete projects and hand over possession on time.
HRERA ruling in Capital Gateway housing project delay
Haryana RERA has directed the builder to pay interest to the complainants against the paid-up amount at the prescribed rate of 10.80% p.a. for every month of a delay from the due date of possession, i.e., June 7, 2015 till offer of possession plus 2 months or actual handing over of possession, whichever is earlier.
The regulatory body explained that the marginal cost of lending rate (MCLR) as on date (June 7, 2026) on SBI website is 8.80%. Accordingly, the prescribed rate of interest will be marginal cost of lending rate +2% i.e. 10.80%.
It also ordered the developer to clear the arrears within 90 days, issue an updated statement of account and not levy any charge not provided for in the buyer’s agreement. HRERA has also asked the developer to pay the complainants Rs 50,000 towards litigation costs.
The Economic Times Business News App for the Latest News in Business, Sensex, Stock Market Updates & More.