SJVN looks to spend Rs 1,200 cr as capex in FY26SJVN is set to invest Rs 12,000 crore in FY26, targeting 13,090 MU of electricity generation, after achieving a record 10,647 MU. In the fi...
SJVN generates 8489 MU power in FY24: CMDState-owned SJVN generated 8,489 million units of green energy from its hydro, solar, and wind power stations in 2023-24. Despite challengi...
SJVN's two plants in Himachal Pradesh produce 50.498 million units of power in single dayTotal generation from all the operational solar and wind power stations of SJVN in the June quarter stood at 101.051 MU, which is 73.04 per...
CCEA to revise Rampur hydro power project cost to Rs 4,233 crBesides, the power from this plant is also distributed to Haryana, Jammu & Kashmir, Punjab, Rajasthan, Uttar Pradesh and Uttarakhand.
SJVN surpasses the MoU targets in power generation, says MDThe mini Navratan central government undertaking had set a target of generating 8,700 million units of electricity, SJVN CMD R N Misra said.
PM Narendra Modi dedicates 3 hydroprojects to nation in Himachal PradeshBHEL's hydro installations are in operation in India and across the world in Azerbaijan, Bhutan, Malaysia, Nepal, Taiwan, Tajikistan, Rwand...
SJVN net income rises 24.53% to Rs 920.35 crore in June quarterState-run SJVN today posted 14.17 per cent jump in standalone net profit at Rs 484.43 crore for the quarter ended June 30 due to higher gen...
SJVN posts record 50.43% rise in PAT for FY15While company's total income increased 50.38 per cent from Rs 1,873. 58 crore to Rs 2,817.53 crore, the PBT (Profit Before Tax) grew by 52....
BHEL adds 736 MW hydroelectric capacity in 2014-15The projects commissioned include two units (200MW each) of Koldam HEP, with which NTPC has made its maiden foray into the hydro sector.
SJVNL targets 8,520 million units of power generation in FY'15-16State-owned power generation utility SJVNL has set a target of producing 8,520 million units of electricity in the current fiscal.
Sutlej Jal Vidyut Nigam commissions all 6 units of 412 MW Rampur hydel projectSutlej Jal Vidyut Nigam (SJVN) today commissioned all 6 units of 412 MW Rampur Hydro Electric Project in Himachal Pradesh.
BHEL commissions sixth unit of 412 MW Rampur hydro plantBHEL said the plant can generate about 1,770 GWh in a 90 per cent hydrological dependable year when all the units are operating.
Swachh Bharat: Sutlej Jal Vidyut Nigam to construct toilets in 350 Himachal schoolsState-run hydropower company Sutlej Jal Vidyut Nigam would construct toilets in 350 schools located in its project areas in Himachal Prades...
BHEL commissions another 68 MW unit at Rampur hydel plantBHEL's scope of work in the project includes supply, erection and commissioning of six 68 MW Francis turbines, among others.
SJVN quarterly net profit jumps to Rs 424 crState-owned power producer SJVN today posted a nearly 24 per cent increase in net profit at Rs 424.29 crore for the three months ended June...
Bharat Heavy Electricals Limited commissions 68 MW hydel unit at Himachal PradeshThe first three units of the Rampur project, which were commissioned earlier by Bhel in March, have been put into commercial operation in M...
- SJVN quarterly profit climbs 29 pc to Rs 411 cr
SJVN recorded net sales of Rs 622.02 crore in the 2011 September quarter as compared to Rs 525.39 crore in the year-ago period.
- BHEL bags Rs 641-cr contract from SJVNL
State-run power equipment maker Bharat Heavy Electricals today said it has bagged Rs 641-crore contract for setting up a 412 MW hydro elect...
- World Bank to extend $4 bn loans to power sector
The financial package would be in the form of loan and half of the lending would be spent in generation and the other half would be spent i...
- WB okays $400mn loan to SJVN for Rampur project
The World Bank has approved a $400 million loan to the Satluj Jal Vidyut Nigam Limited (SJVN) for the development the 412 mw Rampur Hydroel...