Adani Power to acquire 49% stake in Odisha Power for Rs 1,019 croreThe OPGC operates 1,740 MW thermal power plant at Banharpalli in Jharsuguda district, Odisha.
- Sterlite Grid gets letter of intent for Odisha project
Sterlite Grid has received a Letter of Intent for commissioning power evacuation infrastructure in Odisha built with a capex of Rs 1,250 cr...
Centre to examine Odisha govt's push to reallocate coal blocksOPGC has lost both the coal blocks allocated to it after the Supreme Court ordered scrapping of licences of 204 blocks which were allocated...
Odisha optimistic of retaining OPGC's two coal blocksOdisha government today said it had made substantial progress in implementing the expansion plan of the Ib Valley power project.
- Odisha accuses Centre of discrimination in mines allocation
The Odisha government has accused the Centre of adopting a "discriminatory" approach in coal mines allocation.
OPGC awards Rs 1,573-crore contract to BGR Energy SystemsThe order is for OPGC's 2X660 MW thermal power plant with third and fourth units. The project includes development of a captive coal mine a...
- Odisha Power Generation Corporation signs contract with BHEL
After signing the contract, the OPGC MD said BHEL won the international competitive bidding for the job by quoting Rs 4,051 cr.
- ITPS achieves highest yearly PLF
ITPS of Odisha Power Generation Corporation (OPGC) has added one more feather to it's cap by achieving highest yearly PLF of 86.48 per cent.
- OPGC's Unit-1 breaks it's own record of uninterrupted running days
Unit-1 of Odisha Power Generation Corporation's IB Thermal Power Station has achieved a record by running uninterruptedly for 95 days.
- 10 power companies get coal blocks in Odisha: Government
Odisha today said though 10 power generating companies including three state-run public sector undertakings are allocated coal blocks by th...
- OPGC in the eye of storm for violation of CEA guidelines
OPGC, the joint venture company of the state government and US Power utility, AES Corporation, is once again in the eye of storm.
- Environment ministry clears 6 mining proposals in Orissa
Softening its stance on mining in heavily-forested areas, the environment ministry gave its nod for clearing six coal blocks, including fiv...
- Env Min clears 6 coalblocks for 3 power plants in Orissa
Environment Ministry on Wednesday cleared six coal blocks, including five in such areas, for three major power plants in Orissa.
- OPGC to begin work on 1320 MW Orissa power plant in June 2011
Orissa government and US Power utility, AES Corporation have decided to go ahead with third and fourth units at Ib Valley near Banaharpal i...
- Orissa clears rules to prevent child marriage
In a bleated move the cabinet headed by Orissa chief minister Naveen Patnaik on Monday cleared the Rules required to implement the Child Ma...
- OPGC employees union accuse management of corruption, MD denies charges
Orissa Power Generation Corporation Employees Union [OPGC] on Saturday accused the management of indulging in corrupt practices and anti-em...
- OPGC set to go for a brownfield expansion of 1,200 MW
The Orissa Power Generation Corporation announced plans for a brownfield expansion of 1,200 MW, in addition to its existing 420 MW of power...