Essar Power generation up 49 per cent at 11.33 billion units in FY17The generation was up 57 per cent for the January-March quarter of 2016-17 at 2.92 BUs compared to 1.86 BUs in the year-ago period, Essar P...
06 Apr, 2017, 02.55 PM IST
Essar Power Hazira's 2x135 MW power project touches 100% capacity utilisationThe plant can run on multiple fuels, like coal, corex fines and Corex gas, simultaneously. It can also utilize excess gases from the proces...
03 Mar, 2017, 07.16 PM IST
Essar Power's Hazira plant attains 100% capacity utilisation"Essar Power Hazira, a subsidiary of Essar Power, 2x135 MW power project in Hazira was now operating consistently at close to 100% capacity...
03 Mar, 2017, 03.52 PM IST
Essar Power expects to turn profitable this yearEssar Power CEO KVB Reddy, said: "Over the last two years, increased coal availability, both from domestic and overseas suppliers, as well ...
30 Nov, 2016, 02.58 PM IST
Essar Power expects to commission Paradip phase II next yearThe 120 mw imported coal-based power project at Paradip has been set up as a captive power plant to meet the requirements of Essar India’s ...
30 Sep, 2016, 08.29 PM IST
Essar Power expects to commission Paradip Power Plant phase II next yearThe 120 mw project at Paradip has been set up as a captive power plant to meet the requirements of Essar Steel India’s 12 million tonne pel...
30 Sep, 2016, 07.25 PM IST
Essar Power likely to spend Rs 1400 crore on importing coal via online platformEssar Power expects to spend Rs 1,400 crore this year to import coal from countries such as South Africa, Indonesia, Australia, Mozambique ...
30 May, 2016, 05.58 AM IST
Essar Power resumes operations at Mahan unit IEssar Power MP Ltd has secured 6 million tonnes a year coal through e-auction from Coal India subsidiaries.
15 Apr, 2016, 03.34 PM IST
KVB Reddy gets additional charge of CEO at Essar Power MPReddy has more than 32 years of experience in the power industry and has been involved in executing all the power projects of Essar.
08 Mar, 2016, 05.59 PM IST
Over 30 distressed power projects on block, big companies uninterestedIt is a mega discount sale for the festive season. On offer are large power projects at various stages of construction with a combined capa...
04 Oct, 2013, 01.13 PM IST
Essar Energy ropes in top executives from rivals to boost its power businessEssar Energy is changing gears to push its laggard power business by roping in top talent from Reliance Power, Jindal Steel & Power, and GV...
31 Aug, 2013, 04.07 AM IST
Essar Power FY'13 net loss at Rs 512 croreEssar said it will convert two gas fired plants with combined capacity of 1,015 MW to imported coal fired plants with 430 MW capacity.
22 Aug, 2013, 05.02 PM IST
Essar Power bets on coal to meet gas fall, plans to convert two gas plants into coal-based projectsEssar Power plans to convert two of its gas-based power plants in India into coal-based projects as the cost of keeping these plants idle r...
20 Aug, 2013, 05.00 AM IST
Essar Energy planning to convert two gas-fired plants into coal-based unitsThe acute scarcity of natural gas and high cost of imported LNG have taken a toll on Essar Energy's power business.
25 Jun, 2013, 04.15 AM IST
Why executives are moving from PSUs to private sectorMost government employees join private firms post retirement, but there are some who leave early for bright prospects and fat pay packages.
13 Oct, 2012, 06.07 AM IST
- Power generation costs rise by upto 50% over last two years
NTPC, says the cost of generation of one unit of electricity (1,000 watts of power used for one hour) has gone up by up to 20% between 2010...
11 Oct, 2012, 06.53 PM IST
- Essar commissions first generation unit at Salaya
The unit has been synchronised with the state transmission grid and is expected to start commercial production in May 2012.
04 Apr, 2012, 01.56 PM IST