Can bank approach you for home loan recovery as housing project remains incomplete? SC sides with homebuyers, says this
The CJI-led SC bench stated that unless a categorical finding is returned that the homebuyers are in default, no interim direction regarding payment of instalments can be issued. It also directed the civil court not to take any coercive action aga...

Housing project stalled: Can the lending bank initiate recovery proceedings against buyers?(AI-generated representative picture)
The apex court cited the “unholy” nexus between the bank and the builder in which the homebuyer gets caught, and protected the buyers of a failed housing project in Sonipat from any coercive recovery by the State Bank of India (SBI).
"It is the bounden duty of the commercial court to determine the nexus between the builder and bank officials and to see whether the bank disbursed the loan amount to the builder strictly in terms of the tripartite agreement," the SC bench of CJI Surya Kant, Justices Joymalya Bagchi and V Mohana said.
Housing project stalled: Can bank initiate recovery proceedings against buyers?
SC’s big relief to the homebuyers came while it was hearing a plea by the buyers in the Krishna housing project by Raheja Developers, which has gone into insolvency proceedings, according to a report in the Times of India.Homebuyers can’t be asked to repay the loan financier in housing projects that remained incomplete even though banks have released a big portion of loan instalments to rogue or insolvent builders, the top court has clarified.
ALSO READ | Can a pending tenancy rights case stop housing society redevelopment? Maharashtra court clarifies
It further added, “In our considered opinion, it is the duty of the court first to determine the nexus between the builder and the bank authorities and to see whether the bank disbursed the loan amount to the builder strictly in terms of the tripartite agreement.”
Recovery proceedings against Krishna housing project homebuyers
According to the TOI report, the homebuyers in their petition claimed that even though they are yet to receive flats, SBI had begun recovery proceedings against them in a commercial court in Saket, New Delhi.The CJI-led SC bench stated that unless a categorical finding is returned that the homebuyers are in default, no interim direction regarding payment of instalments can be issued. It also directed the civil court not to take any coercive action against the petitioners or similarly placed homebuyers “without first determining the above-mentioned issue".
What was the tripartite agreement between buyers-builder-banks?
Homebuyers had entered into a tripartite agreement with the builder and State Bank of India in order to fund the flats which were under construction in the project. As per the terms of the agreement, the bank was under a legal obligation to disburse the amounts based on the stages of the construction.But the developer failed, and the housing project remained incomplete. The builder has since been admitted into insolvency proceedings before the National Company Law Tribunal (NCLT).
In several cases, however, the loan money was released against each homebuyer because of the builder-bank officials’ nexus. The disbursed amount was much more than what should have been given to the builder according to the construction progress.
Homebuyers’ counsel shared that they had neither received possession of their flats nor the refunds promised under the insolvency proceedings. And despite all of this, SBI filed recovery suits against homebuyers who regularly kept paying the EMIs and the house rent without getting the flats.
ALSO READ | Builder promised 1,395 sq ft flat, parking, compensation in return for property, then issued notice demanding Rs 30 lakh; landowners win over Rs 1.22 crore relief
What should homebuyers do if the bank starts recovery proceedings?
The homebuyer’s liability to the bank depends on the tripartite agreement and the loan documents.Siddharth Batra, Advocate on Record, Supreme Court of India, told ET Wealth Online that under a construction-linked builder-buyer agreement, instalments of the purchase price fall due as the agreed milestones are reached. Loan EMIs are governed by the financing documents.
“In my view, a delay in completing the project does not by itself entitle a buyer to stop paying EMIs that have already fallen due. If recovery proceedings begin, the buyer should respond promptly and raise any objections before the court or tribunal hearing the case.”
Can the bank recover money from homebuyers if it paid the builder ahead of construction progress?
If the bank was required to disburse funds in stages and paid the builder before the agreed milestones were reached, the buyer can challenge the amount claimed and whether there was a default.The court should examine what the bank was entitled to disburse and what the buyer was obliged to repay under the agreements. Premature disbursement does not automatically extinguish the loan, Batra added.
What does this ruling mean for homebuyers?
Even though recovery proceedings were already pending before the commercial court, the Supreme Court granted relief to the homebuyers and directed that the commercial court should first consider the objections of the homebuyers before continuing with the recovery proceedings, said Anjali Jhawar, Advocate, D.M. Harish & Co. LLP, Advocates.In cases where loan recovery proceedings are initiated against homebuyers in a stalled project, in the event the disbursement by the bank does not strictly abide by the construction milestones provided in the agreement between the builder and the bank, the homebuyers can plead non-compliance of the bank with the agreement, she suggested.
The homebuyers can support their defence by relying on incidental documents such as the sanction letter and certificates by engineers/architects for determining the stage of construction of the project.
ALSO READ | Can you earn rental income by letting out your flat on Airbnb for homestay? What homeowners need to know as similar case sparks protests in a Ghaziabad housing society
How to file a claim with a resolution professional if builder goes into insolvency
Although the order referred to concerns banks releasing home-loan amounts to builders without corresponding construction progress, and the resulting repayment liability of homebuyers, it also highlights why buyers must maintain complete documentation if the builder subsequently enters insolvency under the IBC.Pranshu G, Partner at Ashok Pranshu & Co., pointed out that in such a case, the homebuyer should check the public announcement and electronically submit Form CA to the interim resolution professional or resolution professional within the stated deadline.
The claim should specify the principal paid, interest or other amounts claimed, and any refund received.
The buyer should attach the booking form, allotment letter, builder-buyer agreement, demand letters, payment schedule, receipts, cheque copies or UTR details, and matching bank statements.
Where a loan is involved, the sanction letter, tripartite agreement and bank disbursement statement are particularly important.
Relevant correspondence, RERA or court orders, identity proof and a clear interest calculation should also be enclosed.
Further, buyers should retain the proof of filing and the RP’s list of creditors checked.
The Economic Times Business News App for the Latest News in Business, Sensex, Stock Market Updates & More.