Searched for
TAPOVAN PROJECT
Uttarakhand floods: One more body recovered, toll now 62The number of bodies recovered from the intake Adit tunnel of Tapovan-Vishnugad hydel project where a massive search operation has been und...
2 more bodies recovered from Tapovan tunnel; Uttarakhand disaster toll crosses 60Thirteen workers have so far been pulled out of the sludge-choked tunnel at Tapovan where a large number of people were at work when the tr...
Uttarakhand floods: Rescue efforts hampered by water accumulation inside tunnelSludge clearing at the adit tunnel, where eleven bodies were recovered recently, was temporarily suspended since Tuesday evening due to the...
NTPC starts disbursing compensation for deceased workers at Tapovan projectWhile the Tapovan team has accelerated completion of all modalities to fast-track distribution of compensation, the company has decided to ...
Two more bodies recovered from Tapovan tunnel, disaster toll rises to 58While one body was recovered past midnight, another was recovered around 2 am from the tunnel, the official deputed at a temporary mortuary...
Uttarakhand calamity: Three more bodies recovered, toll climbs to 53Rescue efforts are now underway at the Silt Flushing Tunnel (SFT) only with the help of excavators as a camera or apipe cannot be inserted ...
Eight bodies recovered from Tapovan, Raini hydel project sites; toll rises to 46The NTPC's Tapovan-Vishnugad hydel project had suffered extensive damage in the flashflood which also demolished the Rishiganga hydel proje...
Rescue teams battle on in Tapovan tunnelRescue teams battled on against various odds for the sixth consecutive day on Friday to get to the over 30 people trapped inside the sludge...
Uttarakhand Glacier disaster: Rescue operation to locate 25-35 workers trapped inside Tapovan tunnel continuesThe rescue operation at the NTPC hydel project site, which bore the brunt of the disaster, has been going on uninterrupted since Sunday aft...
Uttarakhand disaster: In UP villages, loved ones hover between hope and despairThirty-one bodies had been recovered till Tuesday afternoon from the disaster area as relief workers raced against time to rescue about 30 ...
Fate of NTPC’s Tapovan project hangs in balance after Rs 1,500 crore lossThe company, however, told the BSE on Monday that the “damage may not be considered material or significant” as per Sebi norms in the light...
Uttarakhand glacier disaster: Damage to NTPC project may delay its commissioning, says ministerThe minister visited Tapovan on Monday to assess the extent of damage at the project site, a day after the glacier burst in Chamoli distric...
Toll climbs to 10 in Uttarakhand glacier burst, 143 still missingUttarakhand DGP Ashok Kumar said 143 people are still missing, a day after the glacier burst triggered a massive avalanche and floods in th...
Uttarakhand avalanche: Efforts underway to rescue 30-35 workers trapped in tunnelAround 30-35 people including workers and employees of the 480 mw Tapovan-Vishnugad hydel project on the Dhauli Ganga river are feared trap...
Around 200MW power supply to national grid cut from major plants due to AvalancheEarlier in the day, a glacier broke off in Joshimath in Uttarakhand's Chamoli district which caused a massive flood in the Dhauli Ganga riv...
- NTPC to execute three projects in Uttarakhand
Power major NTPC today said it is implementing three big hydel projects with a total capacity of 942 Mw in Uttarakhand.
- NTPC to invest Rs 3,425 cr in power project
National Thermal Power Corporation Ltd (NTPC) on Friday said it will invest up to Rs 3425.03 crore in Tapovan Vishnugad Hydro Electric Powe...