Over burdened West Bengal Government goes for new hydropower projectsOver burdened with escalation of price for output of upcoming hydroprojects in its northern hilly region, WB is going for four new projects...
- West Bengal will have to pay Rs 600 crore extra per annum for power
West Bengal will have to pay three times higher price for the power to be produced by two major upcoming hydro power stations of total 292 ...
NHPC's Subansiri project sees over Rs 1,000 crore cost overrunFaced with prolonged delays, state-run NHPC has witnessed cost overrun of more than Rs 1,000 crore for its 2,000 MW Subansiri project.
Major hydro power projects of Bengal became victims of Darjeeling bandhTwo major hydropower projects in West Bengal worth Rs 3400 crore have gone under trouble due to indefinite bandh called by a political part...
Mode of divestment will be decided by DoD & Cabinet: ABL Srivastava, NHPC"We have finalised the MoU for 50 megawatt for solar project in case of the UP and this MoU is expected to be signed very shortly."
- West Bengal may need to shoulder heavy loss for overrun in NHPC projects
Hydro electricity projects in West Bengal TLDP III (132 MW) and TLDP IV (160 MW), suffering from heavy time and cost overrun, are finally a...
- Not facing contractual problems in Himachal Pradesh projects: NHPC
In a chat with ET Now, ABL Srivastava, Chairman & Managing Director, NHPC, shares his views on company's performance.
- There is unlikely to be any under recovery in current financial year: ABL Srivastava, NHPC
ABL Srivastava, Chairman & Managing Director, NHPC in a chat with ET Now clarifies that business will not be impacted because of delays and...