Hyderabad govt puts Metro Phase II on fast trackThree corridors have been tentatively identified so far; more lines may be added after considering travel demand and financial viability.
Over 2 lakh passengers travel by Hyderabad metro rail on day 1"On day one of the metro service, over two lakh passengers travelled...it was a record. It was much beyond our expectation," said HMRL MD N...
Hyderabad turns metroland, 1 lakh take first rideMost Metro stations saw serpentine queues at the ticket counters, but even 30-40 minutes of waiting time wasn’t a deterrent for many.
PM inaugurates first phase of Hyderabad MetroThe 30-km-long first phase of the metro rail project between Miyapur and Nagole, having 24 stations, would be thrown open to the public fro...
PM Narendra Modi to flag-off Hyderabad Metro Rail todayDuring its inaugural run, Modi and Telangana Chief Minister K Chandrasekhar Rao will travel by the metro from Miyapur to Kukatpally, and ba...
PM to flag-off Hyderabad Metro Rail tomorrowModi along with Telangana Chief Minister K Chandrasekhar Rao will travel by the metro from Miyapur to Kukatpally, and back.
Trial run of Hyderabad Metro to commence after October 15Reddy also briefed the Board members on the engineering designs and the different stages of progress of urban rejuvenation works being carr...
1st phase of Hyderabad metro rail project to be operational in NovemberThe construction under the project is going on in three phases covering an area of 72 km, Telangana government said.
Bangladesh delegation seeks guidance from Hyderabad metro railA Bangladeshi delegation of senior officers and engineers today called on Hyderabad Metro Rail (HMR) officials, seeking guidance for a Metr...
Work on rail over bridges for Hyderabad Metro Rail starts todayHMR corridors are crossing the tracks of Indian Railways at eight locations in the twin cities with Corridor-I (Miyapur to L B Nagar) havin...
- Hyderabad Metro asks civic body to hand over properties speedily
The matter came up at the special task force's meeting convened here by Telangana chief secretary Rajiv Sharma to review the progress of HM...
Telangana CM Chandrasekhar Rao tells L&T to alter Hyderabad Metro plansThe move comes a few weeks ahead of L&T’s plans to have a trial run along an 8-km stretch between Nagole and Mettuguda before opening the s...
Hyderabad Metro may commence trial run in 6 monthsThe trial-run will commence on the 8-km stretch between Nagole and Mettuguda section of the 72-km metro project and phase-I will be ready b...
L&T Hyderabad Metro rejects allegations of irregularities"L&T is known for its ethics. No money was exchanged nor were we given an extra cent of land," Gadgil said.
Hyderabad metro rail to be opened to traffic by March 2015The first eight-kilometre Nagole-Mettuguda section of the Hyderabad Metro Rail (HMR) will be opened for commuter traffic in March 2015.
- L&T announces Thales as its systems partner for Hyderabad Metro Rail
L&T Metro Rail Hyderabad project will include around 18.5 million square feet of Transit-Oriented Development in the earmarked P&C areas an...
- L&T to commission first phase of Hyderabad Metro Rail by 2014