Homebuyer to get Rs 1.28 crore refund with interest as MahaRERA raps builder for prolonged delay in getting OCA homebuyer will receive a Rs 1.28 crore refund with interest from a builder. MahaRERA ordered the payment after the project failed to get ...
15 Nov, 2025, 12.44 PM IST
MahaRERA steps up project scrutiny to prevent future homebuyer disputesMahaRERA is introducing a three-step scrutiny system—legal, financial, and technical—for project approvals to safeguard homebuyers and prev...
08 Sep, 2025, 04.28 PM IST
MahaRERA: Get quick hearing of RERA cases in these new 7 conditions through priority access; know how it will impact homebuyersMahaRERA has issued new guidelines which specify seven conditions when the RERA authority will hear the homebuyer's case on priority. For o...
29 Apr, 2025, 12.47 PM IST
MahaRERA cracks down on errant builders, freezes 1,950 projects’ bank accountsMahaRERA has frozen bank accounts of over 1,950 stalled or lapsed real estate projects to enforce accountability and protect homebuyers' in...
09 Jan, 2025, 06.44 PM IST
MahaRERA says conciliation forums resolved 1,749 or 32% homebuyers’ complaints so farThe Maharashtra Real Estate Regulatory Authority (MahaRERA) has successfully resolved over 1,749 disputes between homebuyers and developers...
21 Oct, 2024, 11.35 AM IST
NRI homebuyer to get Rs 1.26 crore as refund and compensation from Godrej Properties against cancellation of flat bookingMahaRERA: A non-resident Indian (NRI) paid Rs 97 lakh to book a Godrej flat, however when Godrej cancelled the flat booking, entire money (...
05 Sep, 2024, 05.11 PM IST
Homebuyers empowered by MahaRERA against builders' cheating: Sale agreement to include all these mandatory detailsMahaRERA: Now a promoter can't cheat you with false promises of various facilities and amenities like lifts, gym, etc. As per Subham Chatte...
01 Aug, 2024, 05.11 PM IST
MahaRERA mandates single registration number for each standalone projectAccording to the latest directive, going forward, any promoter seeking new registration for a housing project must submit a declaration-cum...
17 Jan, 2024, 08.23 PM IST
MahaRERA: Buyers to decide fate of incomplete projectsThe promoters, who have failed to meet the deadline after the first extension, would not be able to sell or advertise any of their projects...
06 Mar, 2020, 02.11 PM IST
Home buyers demand fast execution of RERA ordersMany homebuyers and have been in and out of both the civil and MahaRERA courts, fighting battles for incomplete projects.
08 Feb, 2019, 11.20 AM IST
MahaRERA orders ‘remain on paper’Some consumers said issuing orders without ensuring their execution was inconsequential. MahaRERA led the country in terms of disposal of c...
16 Jan, 2019, 01.33 PM IST
MahaRERA invites citizens to become its ‘informers’MahaRERA stated that any alert citizen can now register complaint against the unregistered real estate projects on its website for free, pr...
30 Nov, 2018, 11.06 AM IST
MahaRERA to decide on deals done under earlier law, tooIn a matter related to delay in delivery and compensation for the same, a Mumbai-based realty developer had challenged the authority’s juri...
24 Aug, 2018, 10.58 AM IST
Appellate tribunal of MahaRERA in placeThe permanent appellate tribunal will hear appeals against the orders passed by MahaRERA. Homebuyers and developers can approach it for ove...
16 May, 2018, 12.25 PM IST
MahaRera will keep strict vigil on projects in progressMahaRERA has started a conciliation forum, a platform formed by the members of the Mumbai Grahak Panchayat and developer bodies, such as Cr...
02 May, 2018, 11.26 AM IST
Appellate Tribunal asks MahaRERA to initiate action against architect for incorrect certificateWhile hearing an appeal, the tribunal found out that a builder during a hearing in MahaRERA had said that building has occupation certifica...
13 Apr, 2018, 12.20 AM IST
In first Maharashtra RERA order, builder told to return Rs 26 lakh to consumerThe authority has received more than 98 complaints. On Wednesday, it issued its first order in a case registered by the consumer from Khar.
07 Sep, 2017, 11.31 AM IST