Panel to be set up for monitoring Rs 5,940-cr revised plan to deal with Jharia coalfield fireA monitoring committee will oversee the Rs 5,940-crore revised Jharia Master Plan, addressing coalfield fires and rehabilitating affected f...
Cabinet clears Rs 5,940 crore Jharia Master Plan: The resolution to douse a 100-year-old fire in Jharkhand, explainedThe Union Cabinet has approved a Rs 5,940.47 crore revised Jharia Master Plan to combat the century-long coal mine fires in Jharkhand. The ...
Cabinet OKs revised Jharia Master Plan for fire-control, Pune Metro Phase-IIThe CCEA has approved the revised Jharia Master Plan with ₹5,940.47 crore outlay to tackle underground fires and rehabilitate affected fami...
Coal minister chairs Par panel's meet to discuss way ahead for Jharia Master PlanCoal Minister Pralhad Joshi on Wednesday chaired a meeting of the ministry's Parliamentary Consultative Committee to discuss the way ahead ...
CIL arm CCL seeks reconciliation on Jharkhand's Rs 56,000 cr dues demand from Coal IndiaJharkhand Chief Minister Hemant Soren had on Friday sought immediate payment of Rs 56,000 crore "dues" to the state from the coal giant in ...
Can plug coal import gaps by raising output: CIL CMDAs far as Coal India is concerned, there is absolutely no slowdown. We are not in a position to meet country’s coal demand, CMD Anil Kumar ...
Lethal gases from Jharia's coalfields fire continue to wreck havoc a century laterDumpers belonging to a private company that operates this particular mine ply nonstop, going deep around the spiral and then coming up agai...
Left with some Rs 20,000 crore in cash, Coal India may not be rich as its accounts showCoal India is left with some Rs 20,000 cr only as actual cash balance including some Rs 8,000-Rs 9,000 cr for working capital after paying ...
Government determined to rehabilitate 1 lakh people living near Jharia mines: OfficialDue to unscientific mining in the past, areas near Jharia Coalfields (JCF) and Raniganj Coalfields (RCF), located in Dhanbad district of Jh...
Jharkhand says Reliance Power's Tilaiya exit 'surprising'Reliance Power citing delays in land acquisition and issues related captive coal blocks and infrastructure.
PM Narendra Modi dedicates 765 kv Ranchi-Sipat transmission line to nationIn a slew of inaugurations, PM Modi announced the commencement of work of 3x660 MW North Karanpura Super Thermal Power Project (NTPC).
- Parliamentary Panel for executing Jharia, Raniganj master plan urgently
Parliamentary panel today asked the government to implement the Master Plan for checking fire and land subsidence on "war footing."
- SC concern over handling of fires in coal mines
The Supreme Court today expressed serious concern over the tardy progress in handling the likely consequences of the fires and subsidence o...
- Little hope for trapped miners
Several dead workers were pulled from a coal mine in Jharkhand and there was “little hope” for about 50 miners trapped underground, officia...