Breakthrough in Rishikesh-Karnaprayag project: Railways tackles one of its toughest Himalayan stretches; how close is the 125-km line to becoming operational?

Rishikesh-Karnaprayag project: Indian Railways has achieved a major breakthrough in the 6.59-km-long Tunnel-14 of the Rishikesh-Karnaprayag railway project in Uttarakhand's Rudraprayag district. The milestone connects two excavated sections of the...

Indian Railways has achieved a major construction milestone in the 125-km Rishikesh-Karnaprayag railway project in Uttarakhand, completing the breakthrough in the 6.59-km-long Tunnel-14 in Rudraprayag district. The breakthrough connects two excavated sections of the tunnel, bringing the ambitious Himalayan rail project closer to completion. The tunnel connects a 4.7-km stretch excavated from Portal-1 at Sumerpur with a 1.79-km section from Portal-2 at Marora. The achievement marks an important step in the construction of the railway line, which is expected to improve connectivity across Uttarakhand and make travel to key pilgrimage destinations easier.

Rishikesh-Karnaprayag rail project: How engineers overcame Himalayan challenges

The construction of Tunnel-14 involved several engineering challenges due to the region's complex geological conditions.

Read more - Rs 98 crore Vande Bharat depot at Lower Parel: How Railway plans to transform Dadar into a bigger long-distance train hub with new facilities


A 110-metre triple-track section near Portal-1 passes through loose soil beneath inhabited areas, with an overburden of just 20-30 metres. Engineers used pre-excavation and multi-drifting techniques to carry out the excavation safely.

At Portal-2, the slope was stabilised using 30-35-metre micropiles, 15-20-metre rock bolts and consolidation grouting. The main excavation drive began in March 2024, after ground settlement at Marora and issues concerning land and house acquisition were resolved.

Around 100 metres of excavation at Portal-2 was completed mechanically. Controlled blasting was restricted to daytime near the tunnel portals to minimise risks to nearby settlements. Ventilation systems were also installed throughout the 4.7-km drive from Portal-1.
ADVERTISEMENT

Rishikesh-Karnaprayag railway line: Route, tunnels and stations

The 125-km Rishikesh-Karnaprayag railway project is among Indian Railways' most challenging infrastructure initiatives, involving extensive tunnelling and bridge construction through the Himalayan terrain.

Union Railway Minister Ashwini Vaishnaw highlighted the project's progress on October 22, describing it as a major engineering achievement.

Taking to social media platform X, Vaishnaw said, “Engineering through the Himalayas! 125 km, 12 stations, 83% tunnels. The Rishikesh-Karnaprayag rail line is not just a track; it's Uttarakhand's lifeline to the future.”

The project features 16 tunnels and 19 bridges, reflecting the scale of engineering work required to build a railway network through the mountainous region.
ADVERTISEMENT

How the Rishikesh-Karnaprayag rail project will benefit Uttarakhand

The railway line is expected to improve access to several important towns and pilgrimage destinations, including Karnaprayag and Rudraprayag. It is also expected to provide a boost to tourism and regional economic development.

Highlighting its importance for pilgrims and national security, Vaishnaw said, “Once this project is completed, travel to Karnaprayag, Rudraprayag, and pilgrimages to Kedarnath and Badrinath will become vastly easier.”
ADVERTISEMENT

He also pointed to the railway line's strategic significance, noting that its terminal station at Karnaprayag is located just 123 km from the India-China border.

The project is expected to strengthen transport infrastructure in Uttarakhand while improving connectivity to remote Himalayan areas. Its completion could also make travel for residents, tourists and pilgrims more convenient.


Inputs from agencies
READ MORE
ADVERTISEMENT

READ MORE:

LOGIN & CLAIM

50 TIMESPOINTS

More from our Partners

Loading next story
Business News › Industry › Transportation › Railways › Breakthrough in Rishikesh-Karnaprayag project: Railways tackles one of its toughest Himalayan stretches; how close is the 125-km line to becoming operational?
Text Size:AAA
Success
This article has been saved

*

+