Cabinet approves Rs 1.86 lakh crore electricity grid upgrade scheme
The Union Cabinet has approved a significant Rs 1.86 lakh crore scheme for upgrading the electricity grid. This initiative aims to evacuate 135 GW of renewable energy and establish 50 GWh of battery energy storage. New transmission lines will be a...
He emphasised that managing the high variations in renewable energy, like solar and wind, is a "major challenge," stating, “The grid has to be designed to take the load of that variation.”
Also Read: Data centre surge triggers CEA study on grid stability
An official statement said brownfield upgradation and network strengthening works will be executed under Cost Plus Basis (CPB). The State Transmission Utilities will be the overall implementing agency, and Transmission Service Providers (TSPs) will participate under TBCB on a Build-Own-Operate-Maintain (BOOM) model.
“The scheme will help in achieving the target of 900 GW installed Non-Fossil capacity by 2035,” the statement added.
Also Read: Power Mech Projects bags Rs 549 cr O&M order from Adani Group entity
An official presentation said Green Energy Corridor Phase-III scheme which aims for states to set up intra-state power transmission by fiscal 2032-33. Under the program, the renewable energy developers will also get support for setting up battery energy storage projects of 50 GWh capacity, for which the scheme has kept Rs 50,000 crore.