In 1987, Kansas crushed three gravel roads, mixed them with power-plant fly ash, and rebuilt them in place; the method later spread across more than 400 miles
Kansas workers revolutionized road reconstruction in 1987 by introducing a novel technique using pulverized gravel. This method involved blending fly ash with existing road materials, resulting in a robust foundation. The successful implementation...

The work was part of a demonstration program funded by the Electric Power Research Institute (EPRI). A 1994 report from the Transportation Research Board describes the three roads and the construction steps. It also reported that more than 400 miles of Class C fly ash pavement recycling had been completed in Kansas and Oklahoma.
The old gravel became the new road base
The crews first broke down the existing gravel surface until it could be mixed. A pneumatic tanker spread Class C fly ash over the loosened road material. The ash content ranged from 10 to 20 percent of the dry matter. The ash was then mixed with the pulverized gravel in a recycling machine. The blended material was placed back along the road and compacted to form the base course, which is the layer that supports the surface above it. A seal coat was added to finish each of the three roads. The key difference was that the existing road material remained on site.
What the ash contributed
Fly ash is a very fine powder captured from the gases generated by the burning of coal in a power plant. Class C fly ash, used in Kansas, is created from certain coals and is capable of forming cement-like compounds when it comes in contact with water. That reaction caused it to be considered a candidate for use in binding loose road material. This experiment tested the ash as part of a road base, not as a replacement for the finished driving surface. This compacted mixture carried the load beneath a separate seal coat. Since Class C ash is typically produced from lignite or subbituminous coal, this was a trial of the use of a power plant byproduct in road construction. The results would still be dependent on the road and mix.
From a demonstration to wider use
The three county roads were the starting point, not the total mileage. The Transportation Research Board’s 1994 synthesis says that after the first locations were reconstructed, over 400 miles of pavement recycling using Class C fly ash had been completed in Kansas and Oklahoma. The larger number indicates that the technique was not limited to a single demonstration, but should not be interpreted as 400 miles in Kansas alone. The report gives the combined distance for Kansas and Oklahoma and does not break it down by state.
What the three-year record could reveal