A Washington dam blocked fish from reaching part of a creek for nearly 60 years; after its removal in 2024, steelhead were spotted again in the restored waterway
Pete Barber led a project that removed Kwoneesum Dam, restoring essential fish habitats along Wildboy Creek. This effort, which took seven years, reconnected fish to upstream spawning areas and improved water temperatures. In June 2025, adult stee...

An AI-generated representative image of a restored forest stream, illustrating the type of habitat reopened for salmon and steelhead after the removal of Washington's Kwoneesum Dam. (Image credit: ChatGPT)
The 55-foot Kwoneesum Dam was taken down in October 2024. Almost a year later, adult steelhead were seen in the restored stretch, and workers found their spawning nests, known as redds. It was an early sign that fish could use a stretch of Wildboy Creek blocked for almost 60 years.
A camp reservoir became a barrier
The dam was built in 1965 by the Camp Fire Girls organization to create a nine-acre reservoir for summer camp activities. The camp was later closed, but the reservoir remained. The barrier, however, had dire consequences for fish. Steelhead and salmon were not able to get around the dam to reach their upstream spawning grounds. The reservoir also warmed up in the summer, with water spilling over an outlet to create a 30-foot waterfall. Water temperatures were as high as 75 degrees, too warm for salmon and steelhead. The dam also prevented the movement of gravel, rocks, and fallen trees. In healthy streams, fish rely on streambeds and pools formed by gravel and wood to spawn and shelter young fish. The creek was scoured to bedrock downstream.
A seven-year effort to remove it
It took seven years to remove the dam. The 1,300-acre property was purchased by Columbia Land Trust in 2020, and the Cowlitz Indian Tribe was collaborating to secure funding for the dam removal and stream repair. There were three tributaries that fed the reservoir, and crews initially diverted the flow of these tributaries with screened pumps. They pumped approximately 20 million gallons of water and installed porous geotubes to catch fine sediment. Contractors then used excavators and jackhammers to break the concrete and rock apart, one section at a time. The main work was finished in October 2024.
Rebuilding a creek, not just removing a dam
Access was reopened by removing the barrier, but fish also required appropriate habitat. The project team rechanneled and rerouted sections of the streambed with rock, gravel, and boulders and reconnected channels that were covered by the reservoir. Crews placed logjams, meaning logs across the creek, to create pools and slower water to provide a place for young fish to hide. According to NOAA Fisheries, removing barriers can reopen important spawning and rearing habitat for salmon and steelhead. The project therefore reopened 6.5 miles of spawning and rearing habitat and enhanced 1.3 miles of stream channel. It also included 75 logjams and 12 pools for juvenile fish to hide in. The project planted 37,550 native trees and shrubs to reforest the dam reservoir footprint by the Cowlitz Tribe and its partners. As they mature, the plants will shade the water and help to keep it cool.
Steelhead begin exploring the reopened reach

The next stage is a living stream
The team expects substantial vegetative cover to become established throughout the creek drainages within a year or two of planting. The next phase is to determine if fish continue to reproduce as expected and whether this tributary system continues to provide adequate habitat and sustenance for juvenile salmon. The Cowlitz Indian Tribe is also pursuing another project to remove a barrier on nearby Ostrander Creek, which blocks access to another 13.9 miles of fish habitat.
The Economic Times Business News App for the Latest News in Business, Sensex, Stock Market Updates & More.