Bengaluru Namma Metro Blue Line moves closer to launch: Trial run begins as 11-12 lakh tech employees await ORR connectivity; when will passenger services start?
Bengaluru's Namma Metro Blue Line has begun trial runs, with further testing planned in the coming months. The Phase 2A corridor will connect KR Pura to Central Silk Board through thirteen stations. However, passengers should anticipate a delay of...
The initial trial runs have started on the KR Pura-Doddanekundi stretch, covering the first four stations. BMRCL plans to extend the testing exercise to another four stations next month as work progresses along the corridor.
Greater Bengaluru Development Minister Krishna Byre Gowda inspected the new trains at Doddanekundi station on Monday, accompanied by Bengaluru Central MP PC Mohan, Mahadevapura MLA Manjula Limbavali and senior BMRCL officials.
The 19-km Phase 2A corridor will connect KR Pura to Central Silk Board through 13 stations. Once operational, the Blue Line is expected to provide an alternative transport option for around 11-12 lakh people working along the busy ORR stretch, which is home to several major IT parks and technology campuses.
When will Namma Metro Blue Line open for passengers?
Despite the commencement of mainline trials, the corridor is unlikely to open for public use immediately, as several crucial infrastructure and signalling works remain incomplete.The installation of the automatic signalling system is expected to take another two to three months. This will be followed by mandatory testing, safety inspections and statutory approvals before passenger services can begin.
Gowda said the government aims to complete the signalling work by January, with the certification process expected to begin after February. Taking the remaining testing and approval procedures into account, the corridor could require another seven to eight months before opening to commuters, with operations targeted for the middle of next year.
Why will the Blue Line take another 7-8 months to become operational?
The start of train trials has raised expectations among Bengaluru's office commuters, particularly those working along the Outer Ring Road. However, BMRCL still needs to complete several infrastructure and systems-related tasks before the corridor can accommodate passengers.BMRCL has received two trainsets from BEML, with additional deliveries expected according to the agreed schedule. However, space constraints at the depot have affected the accommodation of more trains. Officials expect these issues to be resolved by February, allowing additional trainsets to be inducted.
Explaining the importance of starting trials on the mainline, BMRCL Managing Director PC Jaffer said the development indicated that civil and track-related work had progressed sufficiently to allow further testing and signalling installation.
“Getting a train on the mainline means the civil and track works are clear of major obstructions. This will facilitate signalling work,” he said.
Will the entire Blue Line open at once or in phases?
BMRCL has not yet decided whether to introduce passenger services across the entire 19-km corridor at once or open the stretch in phases.According to Jaffer, operating the line in phases could involve additional logistical challenges and require nearly the same amount of time and effort as commissioning the complete corridor.
“We have not taken a call on this yet. Opening the line in phases is more challenging and requires almost the same effort and time. We will review the progress before taking a decision,” Jaffer said.
What safety approvals are required before passenger services begin?
Before the Blue Line can start commercial operations, BMRCL must obtain several mandatory safety clearances.These include an independent safety assessment of the signalling system, testing by the Research Designs and Standards Organisation (RDSO) and final authorisation from the Commissioner of Metro Railway Safety (CMRS).
The inspections will assess whether the trains, tracks, signalling equipment and other safety systems meet the requirements for passenger operations. The time needed to complete these procedures will also influence the corridor's opening schedule.
On the supply of trains, Jaffer said the two trainsets received from BEML were sufficient for the ongoing trial runs. The manufacturer is scheduled to supply a total of 66 trainsets for the Blue Line.
Namma Metro Blue Line trains to have dedicated luggage space
The upcoming Blue Line will introduce a dedicated luggage facility in Namma Metro trains for the first time. The feature has been included keeping in mind the airport connectivity that the corridor will provide through its connection to Kempegowda International Airport (KIA).Dedicated luggage spaces will be available in four coaches of every train, allowing passengers to carry suitcases and other bulky baggage more conveniently.
However, the additional facility will reduce seating capacity. According to officials, seating equivalent to 16 passengers will be removed from each of these four coaches compared with the coaches currently operating on the Purple and Green Lines.
What is the financial position of BMRCL?
Meanwhile, the state government has assured continued financial assistance to BMRCL to support its loan repayments and operational losses.Gowda said the depreciation of the rupee against the US dollar had increased the corporation's borrowing costs and repayment burden. He pointed out that the dollar, which was around Rs 70-80 when the loans were taken, had risen to nearly Rs 100, increasing the repayment burden by approximately 30%.
The financial pressure on the corporation has also increased despite higher metro ridership and revenue. BMRCL's loss before tax rose to Rs 1,717.4 crore in the last financial year, compared with Rs 691.6 crore in the previous year. Finance costs more than tripled to Rs 1,793 crore, alongside an increase in depreciation expenses.
The state government is providing support to ensure that these financial challenges do not affect ongoing and proposed metro projects.
[With TOI inputs]