MPCB asks Adani firm to stop excavation work for temporary labour shed in Satara

Maharashtra Pollution Control Board issued a stop-work notice to Adani Renewable Energy One Ltd for unauthorized excavation. The notice pertains to a temporary labour camp related to a 1500 MW project in Satara district. The company commenced work...

Mumbai: The Maharashtra Pollution Control Board (MPCB) has directed Adani Renewable Energy One Ltd to stop excavation and construction work for its temporary camp in Satara district for allegedly beginning these without obtaining the necessary environmental clearance and permissions.

The labour camp in Satara's Patan taluka, some 300 kilometres from here, is part of the firm's 1500 MW Tarali Pumped Storage Project.

In a stop-work notice dated November 20, the MPCB said the company had started excavation and development work at Gat Nos. 33 and 34 in Sawargahar village for a temporary labour camp and other storage activities without informing the board or obtaining the required permissions.


Read more: Adani Green says Tarali Project has no protected area or forest land overlap

The company had not secured environmental clearance for the excavation and development work from the competent authority, the MPCB added.

The notice, issued under Section 33A of the Water (Prevention and Control of Pollution) Act 1974, and Section 31A of the Air (Prevention and Control of Pollution) Act 1981, directed the company to stop all ongoing and proposed excavation and construction activities forthwith.
ADVERTISEMENT

It further prohibits the resumption of any activity without prior permission from the MPCB, warning that failure to comply would invite legal action under the relevant environmental laws.

Read more: Adani Green surpasses 20 GW renewable energy capacity, first in India to hit milestone

The MPCB said its officials visited the project site on November 20, following which the Satara sub-regional officer submitted a proposal for legal action.

"MPCB had granted the company consent to establish the 1,500 MW standalone pumped storage project in April 2025, subject to certain terms and conditions," the notice said.
READ MORE
ADVERTISEMENT

READ MORE:

LOGIN & CLAIM

50 TIMESPOINTS

More from our Partners

Loading next story
Business News › Industry › Renewables › MPCB asks Adani firm to stop excavation work for temporary labour shed in Satara
Text Size:AAA
Success
This article has been saved

*

+