Technology denial and infra crunch have delayed DRDO projects: Government

Defence Minister Manohar Parrikar said in the Rajya Sabha that as on date, there are 294 ongoing projects with a cost of more than Rs 2 crore each in the DRDO.

Technology denial and infra crunch have delayed DRDO projects: Government
NEW DELHI: Non-availability of infrastructure and test facilities in the country, denial of technology by other nations and development of state-of-the-art technologies from the scratch are some of the reasons for delay in ongoing DRDO projects, Rajya Sabha was told today.

Defence Minister Manohar Parrikar said in the Rajya Sabha that as on date, there are 294 ongoing projects with a cost of more than Rs 2 crore each in the DRDO.

While 60 are mission mode projects, 144 are technology development related, 62 relate to science and technology, five are for product support and 23 relate to infrastructure and facilities.

In a written response, he said some of the ongoing projects are delayed due to ab-initio (from the scratch) development of state-of-the-art technology, technological complexities, non-availability of infrastructure and test facilities in the country, non-availability of critical components, denial of technology by countries and failure of some components during trials.

Parrikar said consortium approach is being used for design, development and fabrication of critical components to overcome delays. Also, information technology and modern management techniques are being applied.

Joint funding by users are being encouraged to ensure their commitment towards earliest completion of project, he said.
ADVERTISEMENT

During the last three years and current year, DRDO has successfully completed 45 projects costing over Rs 2 crore each, the Defence Minister said.
Download
The Economic Times Business News App
for the Latest News in Business, Sensex, Stock Market Updates & More.
Download
The Economic Times News App
for Quarterly Results, Latest News in ITR, Business, Share Market, Live Sensex News & More.
READ MORE
ADVERTISEMENT

READ MORE:

LOGIN & CLAIM

50 TIMESPOINTS

More from our Partners

Loading next story
Business News › News › Science › Technology denial and infra crunch have delayed DRDO projects: Government
Text Size:AAA
Success
This article has been saved

*

+