How LAC tension is delaying work on Mumbai coastal road
As per reports, eight of 18 tunnel boring machines (TBMs) currently in the city for the Metro 3 project have been manufactured by Chinese-owned firms. The remaining 10, though are by companies registered in the West, too have been manufactured i...

“Around 100 pieces of the TBM, imported from China, need to be put together. Because of India-China tensions, contractor L&T has been unable to get clearances for engineers from the Chinese manufacturer to reach Mumbai for the work. But Chinese engineers already working on the TBMs being used in Metro 3 and the Bangalore Metro can help assemble the coastal road TBM, the biggest in India, as the Metro TBMs are similar machines, size being the only difference,” said a BMC official.
“After the machine is assembled, we need to test it to start the actual work. But even for that we need engineers from the Chinese company that manufactured the machine. It was tested in China in December 2019, before being dismantled for shipping to India, but a test needs to be done again after it is assembled,” the official said.
As per reports, eight of 18 TBMs currently in the city for the Metro 3 project have been manufactured by Chinese-owned firms. The remaining 10, though are by companies registered in the West, too have been manufactured in China.
The Economic Times Business News App for the Latest News in Business, Sensex, Stock Market Updates & More.
The Economic Times News App for Quarterly Results, Latest News in ITR, Business, Share Market, Live Sensex News & More.