CAG blames Maharashtra Government for Rs.26,617 crore cost overrun in irrigation

CAG has criticised the Maharashtra government for irregular extra expenditure on irrigation projects and these projects remaining incomplete for over 40 years.

MUMBAI: Maharashtra's Deputy Chief Minister Ajit Pawar and his party NCP is likely to face some fresh political trouble as the latest report presented by the Comptroller & Auditor General ( CAG) has rapped the water resources ministry for serious cost overruns in many irrigation projects. Ajit Pawar controlled the water resources ministry for nine years between 2000 and 2009.

CAG has criticised the Maharashtra government for irregular extra expenditure on irrigation projects and these projects remaining incomplete for over 40 years. CAG in its report for the year ended March 2012, said over Rs 43,000 crore were spent by the Water Resources Department on 426 projects in the state and most of them still remain incomplete.

The Congress NCP government, which is already under fire from the opposition parties for the irrigation scam, will now face more criticism in view of this latest CAG report.

According to CAG, in 242 irrigation projects the initial budget cost rose to Rs 33,832 crore from Rs 7,215 crore, resulting in a cost overrun of Rs 26,617 crore. The list of projects with the major cost overrun above Rs 800 crore include Kukdi (overrun is Rs 2,152 crore) , Krishna Marathwada irrigation project ( Rs 2,462.55 crore) , Lower Dudhna project (Rs 997 crore), Nandur Madhmeshwar project (Rs 817 crore), Waghur project (Rs 1,171crore) and many other projects.

CAG has said in it's report that though many irrigation projects commenced 45 years ago, they are not yet complete. The oldest being Kudki project, in respect of which the year of commencement was 1967 with a target date of completion of five years (1972). CAG observations come at a time when the Maharashtra Government appointed special investigation team (SIT) led by water expert Madhav Chitale is investigating the irrigation scam.

CAG had found irregularities in the irrigation expenses in earlier reports too. Just two days ago CAG told the Bombay high court that it stood by its report that found irregularities in irrigation projects in Maharashtra. CAG, in its 2011 report, had pointed out several irregularities in the irrigation projects undertaken by the Government in the state in the last 10 to 12 years.

Download
The Economic Times Business News App
for the Latest News in Business, Sensex, Stock Market Updates & More.
Download
The Economic Times News App
for Quarterly Results, Latest News in ITR, Business, Share Market, Live Sensex News & More.
READ MORE
ADVERTISEMENT

READ MORE:

LOGIN & CLAIM

50 TIMESPOINTS

Related Companies

More from our Partners

Loading next story
Business News › News › Politics › CAG blames Maharashtra Government for Rs.26,617 crore cost overrun in irrigation
Text Size:AAA
Success
This article has been saved

*

+