Real-life Temple Run in Pakistan: PKR 1 billion road turns into real-life obstacle course as cars dodge 50 live electric poles; watch video
A Rs 1.06-billion road in Pakistan's Hyderabad has turned into an unexpected obstacle course, with live electricity poles standing in the middle of the newly constructed carriageway. A viral video shows motorists swerving around the poles to navig...

The poles carry high-tension electricity lines originating near the 132-kV grid station in Qasimabad, which supplies power to a substantial part of Hyderabad. Videos showing the road lined with these structures began circulating on social media a few days before the latest clip attracted more than 87,000 views on X.
Also Read: No free electricity for Bihar taxpayers? CM appeals to income-tax payers to surrender 125-unit benefit and support state's development
Why are electricity poles standing in the middle of Hyderabad's new road?
The road connects Alamdar Chowk with the old National Highway near Qasim Chowk in Sindh province. Its construction was taken up in an area that had previously remained largely abandoned before the road project was approved.The development work and the relocation of electricity infrastructure were being undertaken simultaneously, leaving several power poles along the carriageway. The situation prompted questions about how the road could be opened to traffic before all the obstructions were removed.
Hyderabad Deputy Commissioner Zainul Abedin Memon said the road had not been formally opened and that barricades and warning signs had been installed to restrict public access. However, commuters continued to use the stretch despite the restrictions.
Power company explains why the poles are still in the road
HESCO spokesperson Sadiq Kubar told Dawn the 132-kV Qasimabad grid station near Alamdar Chowk supplies electricity through 27 feeders. Of these, 24 pass through the area where the road has been constructed.He said 22 of the 27 feeders had been transferred to new poles and energised, while work on the remaining five was still pending. The spokesperson also explained that 100 high-transmission lines needed to be relocated as part of the exercise.
Officials said 97 electricity poles had been shifted by October 28, with the remaining structures expected to be relocated by November 10.
Hyderabad road part of three projects worth Rs 1.06 billion
The 1.6-km dual carriageway is one of three road development projects with a combined estimated cost of Rs 1.06 billion. The newly built stretch is a significant addition to Hyderabad's road network, connecting the city's bypass with Qasim Chowk road.The project has nevertheless come under scrutiny because electricity infrastructure was still present along the route after the road was constructed. The competing timelines for road development and the relocation of power lines have become the focus of the online criticism.