Oregon’s bridge program diverted 640,162 tons of construction material from landfills; FHWA valued the landfill diversion at $21.3 million across 208 bridges
Bundled bridge contracts streamline multiple projects into a cohesive framework, enhancing efficiency and minimizing costs. This strategy promotes the recycling of materials and helps reduce landfill waste. Additionally, contractors benefit from e...

Representative Image: Bundled bridge contracts streamline multiple projects into a cohesive framework, enhancing efficiency and minimizing costs. This strategy promotes the recycling of materials and helps reduce landfill waste. Image Credits: Google Gemini
Oregon’s OTIA III State Bridge Delivery Program provides one example of how bundling was used alongside material-recovery measures. Approved by the Oregon legislature in 2003 as part of a 10-year transportation package, the programme repaired 122 and replaced 149 state-owned bridges. FHWA says the programme was completed on schedule and $45 million under budget. Over its life, 640,162 tons of material were recycled, while the estimated value of diverting materials from landfills was $21.3 million. FHWA separately notes that 208 bridges received permits over six years, so those figures should be understood as programme-wide results rather than an average applied to each permitted bridge.
The Oregon programme also illustrates why agencies may bundle projects along the same travel corridors. FHWA says grouping bridges allowed contractors to gain economies of scale in design, material ordering, equipment mobilisation, and other resources. The programme also reused 30,000 cubic yards of rubble from one bridge as aggregate on another OTIA III project, showing how material recovery could be incorporated into a broader construction programme.
How contract bundling improved bridge projects
The benefits documented by FHWA extend beyond material management. Bundling can allow agencies to coordinate work across several structures instead of managing each project independently, potentially reducing duplication in design, procurement, mobilisation, and project administration. Grouping bridges by location or type can also give contractors a more predictable workload and allow equipment and crews to be deployed across multiple sites.
Several of the programmes highlighted by FHWA were designed specifically to accelerate bridge repairs. Missouri’s Safe and Sound Bridge Improvement Program, for example, bundled 802 bridges into two procurement packages and completed the work in three and a half years, more than a year ahead of its expected schedule. FHWA says the revised approach also saved more than $500 million compared with the cost of an earlier design-build-finance-maintain concession proposal. The programme reduced the average closure period for 493 bridges to 42 days.
Massachusetts provides a separate example of accelerated delivery rather than the same type of documented financial saving. Its Accelerated Bridge Program, established in 2008, used design-build delivery, extended work hours, prefabricated bridge components, rapid-strength-gain concrete, and other measures to speed construction. FHWA also highlights the I-93 FAST 14 project, where 14 bridges were replaced as part of the accelerated approach. These examples show that bundling and related delivery methods can support faster construction, but the programmes should not be treated as evidence that every bundled project produces the same cost or schedule results.
The historical programmes also demonstrate how bundling can support local construction industries. In Oregon, 86% of programme contracts were awarded to Oregon-based firms, according to FHWA, while the programme supported thousands of jobs over its lifespan. Missouri likewise reported that more than 90% of the work was performed by Missouri workers. These outcomes show how large, coordinated infrastructure programmes can create opportunities for local contractors and suppliers while delivering multiple projects through a common procurement strategy.

The bridge-bundling programmes documented by FHWA are largely historical case studies, but their methods provide lessons for agencies planning infrastructure work today. Oregon’s OTIA III programme began in 2003 and ran for a decade, while Missouri’s Safe and Sound programme and Massachusetts’ Accelerated Bridge Program were also carried out in earlier periods. They should therefore be understood as completed examples of project delivery rather than contemporary programmes still under construction.
Their results nevertheless demonstrate how coordinated planning can influence the cost, schedule, environmental performance, and public impact of major bridge programmes. Oregon’s experience is particularly notable for combining project bundling with environmental permitting, traffic management, material recycling, and resource planning. FHWA says the programme used 67 project bundles and incorporated environmental performance measures into the delivery process.
For transportation agencies facing large backlogs of ageing bridges, these past programmes offer a practical set of lessons. Grouping suitable projects, planning material use, coordinating permits, and deploying crews and equipment across multiple sites may help agencies make more efficient use of infrastructure funding. The FHWA case studies do not establish that bundling will automatically reduce costs or construction times in every setting, but they show how states have used the approach to pursue those goals while also addressing traffic, environmental, and workforce considerations.
The Economic Times Business News App for the Latest News in Business, Sensex, Stock Market Updates & More.
The Economic Times News App for Quarterly Results, Latest News in ITR, Business, Share Market, Live Sensex News & More.