Colorado rebuilt part of US 24 by reconditioning its old asphalt in place; the $5.7 million project avoided hauling in more than 40,000 tons of new base
Colorado has made strides in sustainable road maintenance with the successful recycling of old asphalt on US Highway 24. By saving over 40,000 tons of new base material and lessening transportation requirements, this project exemplifies an innovat...

Rebuilding roads with recycled asphalt (representative image). Image Credit: ChatGPT
What in-place asphalt recycling means for a highway contract
Usually, a major highway reconstruction takes the form of a loop: break up the old road, haul the debris to a landfill or recycling center, then bring in new base material from a quarry by the truckload. Each step adds cost, emissions from transport vehicles, and traffic congestion in the construction area. On westbound US 24, CDOT milled the old asphalt pavement and reconditioned the roadway base before paving over it with new concrete pavement. This combination, a recycled asphalt base topped with a new concrete surface, is a recognized approach in highway engineering; a stabilized base built through full-depth reclamation can support either an asphalt or concrete top layer. The agency also used an on-site concrete batch plant during construction, which reduced the need for ready-mix trucks from an outside supplier.
US 24 rebuild by the numbers: material savings and speed
According to CDOT's own project release, by reprocessing the pavement on-site, the project saved over 40,000 tons of new base course material, which the agency estimates is roughly 1,600 loads that would not have had to make the trip. The work also moved quickly, with crews laying more than 14,800 cubic yards of concrete in under two weeks, all of it made at the on-site batch plant. Both directions of US 24 had been narrowed to one lane since late June while the westbound side was being reconstructed, so a quick turnaround was critical to traffic flowing over that corridor every day.

Why recycled road base saves money for drivers and taxpayers
For drivers, fewer material deliveries through a work zone can mean fewer disruptions on nearby streets. For taxpayers, reusing the material under the road instead of buying and hauling in new rock and gravel can cut costs because fuel, equipment hours, and disposal fees add up on a standard tear-out-and-replace project. Reclaiming full-depth pavement isn't an answer for every road. However, engineers study the existing pavement and underlying soil before recommending it, and some stretches of highway still require new construction. For a major commuter corridor like this section of US 24, recycling the old base made more sense.
CDOT's rebuild of US 24 included intersection work at the US 24/Garrett Road intersection and Sand Creek culvert scour repairs, with the full project scheduled for completion in fall 2017. The next time you see a stretch of highway repaved faster than expected, the crew may have recycled the base material in place instead of hauling it away.