AI boom sends power bills soaring across the US grid
Electricity bills are rising in several US states. The reason is the increasing demand from data centers powering artificial intelligence. PJM Interconnection manages the electricity grid. Capacity auction prices have jumped. Experts suggest refor...

Plug prices, rather than pump prices, are igniting a political firestorm. In New Jersey, the latest flashpoint, utility bills figure prominently in a gubernatorial race that has gained national attention and is less than three months from election day. And at the heart of all this is the race for artificial intelligence.

Now for the bad news: These residential billing data only run through May. That was just before the impact of a monumental jump in capacity prices, based on an auction run by PJM last year, kicked in. This chart of more up-to-date wholesale prices shows further pain is coming.

Capacity auctions set payments to generators that encourage them to keep existing plants open or build new ones, separate from the revenue they earn for actually producing electricity. This is a crucial, if arcane, corner of the power market and its shock will stick because it gets set for a year at a time — and the latest auction, for the year beginning June 2026, came in even higher.
After many years of flat electricity demand, PJM now forecasts an imminent jump, and it takes time — as well as spiking price signals — for energy supply to react. The culprit is the AI boom, with PJM serving Virginia’s burgeoning data center alley. Some 64% of those ballooning capacity payments that began hitting bills in June relate to actual and projected datacenter demand, according to Monitoring Analytics’ calculations.

The auction itself needs fixing. Hugh Wynne, utilities analyst at Sector and Sovereign Research LLC, compares it to a “rain dance” that doesn’t deliver what it is supposed to: New capacity. The inflated costs of the last two auctions are enough, by his calculation, to fund 19 gigawatts of new gas-fired capacity, yet cleared only four gigawatts of actual new additions. The result is a transfer of a wealth from homeowners mostly to existing generators for little reward.
Part of the problem is timing. Auctions are supposed to set prices several years out but delays have shortened that period to less than 12 months, completely inadequate for planning plants that take years to construct. In addition, PJM has adopted more conservative assumptions for the reliability of different types of generation. While these are shaped by the poor performance of plants during prior extreme weather events, they effectively reduce the total capacity assumed to be available, thereby driving up the auction price, and may be worth revisiting given lessons learned from those episodes.
PJM has implemented or proposed several reforms, such as expanding participation by certain types of generation. Wynne suggests splitting the capacity market into one for existing plants and another for new capacity, thereby offering more surety of pricing for the latter and, presumably, less of a windfall for the former.
It would be absurd to abandon the benefits of decades of deregulation just to accommodate data centers; rather, the onus is largely on them. At a minimum, they should be required to effectively bring their own power, committing to long-term power purchase agreements to support new plants, not just signing contracts for existing capacity. That new capacity would increase the grid’s resilience overall, shifting datacenters from being a challenge to being part of the solution. In return, such plants could be given priority in terms of permitting and interconnection.