Bengaluru Metro's Yellow line gets a boost: Titagarh rail systems to deliver first trainset in August
Titagarh Rail Systems Limited has started producing trainsets for the Bangalore Metro Rail Corporation Limited's Phase 2 Yellow Line project, a contract with China Railway Rolling Stock Corporation. The first trainset is scheduled for delivery in ...

Production officially began on May 18, 2024, the company said adding that the first trainset is scheduled for delivery in August 2024.
Notably, the 21-km Yellow Line, stretching from RV Road to Bommasandra, is a vital metro corridor aimed at improving connectivity and reduce traffic congestion in the tech hub.
The contract, initially signed in December 2019 between BMRCL and CRRC Nanjing Puzhen Co Ltd, faced several delays, prompting CRRC to seek additional time for delivery.
Following this, CRRC entered into a Memorandum of Understanding (MoU) with Titagarh Rail Systems.
Under the agreement, Titagarh is responsible for producing 34 of the 36 trainsets required for the Yellow Line, with only two trainsets, comprising 12 coaches, to be manufactured in China.