Necessary approvals reduced for setting up factory in MIDC area
A total of 14 approvals by MIDC were required so far at the pre-commissioning stage. It will be brought down to five, an official said.

A total of 14 approvals by Maharashtra Industrial Development Corporation (MIDC) were required so far at the pre-commissioning stage. Now, it will be brought down to five, an official in the Chief Minister's office said.
The required permissions would be for land allotment and lease, mortgage, building plan approval, final fire NOC and building completion certificate, he said.
All other nine NOC permissions have been done away with.
The labour department has notified new rules to enable renewal of factory licence in three days, or the application will be deemed renewed.
Similarly under the Bombay Shop and Establishments Act, new permission will be granted in three days or the application will be automatically considered as deemed approved.