National Green Tribunal asks MoEF to finalise Gadgil panel report on Western Ghats
A bench headed by NGT Chairperson Justice Swatanter Kumar has granted the MoEF three weeks time, as a last opportunity, to finalise the report.

A bench headed by NGT Chairperson Justice Swatanter Kumar has granted the MoEF three weeks time, as a last opportunity, to finalise the report and place it before the Tribunal.
"Needless to notice that this is a matter of some urgency and it is expected from the MoEF to take expeditious steps to finalise acceptance or otherwise of Gadgil Committee Report or any other Committee Report.
"As prayed, we grant three weeks time to the MoEF by way of last opportunity to finalise the report and place before the Tribunal its clear stand," the bench said, and listed the matter for further hearing on April 25.
The NGT passed the order on April 2 after Kerala submitted that non-finalisation of the Gadgil panel report is affecting the state's commercial activities and development.
In its report submitted to the MoEF in August 2011, the Gadgil Committee, also known as the Western Ghats Ecology Expert Panel (WGEEP), had designated the entire Western Ghats as an 'ecologically sensitive' area.
Meanwhile, the counsel for MoEF has submitted that the tenure of the working group, headed by Planning Commission member K Kasturirangan, set up to finalise the Gadgil panel report has been extended till April 15, the day when the complete report would be made available to the ministry.
The NGT was hearing a plea by NGOs from Goa, Kerala and Karnataka against grant of any clearance to any new project in ecologically sensitive Western Ghats and implementation of the WGEEP's report on the protection and preservation of the area.