Draft Scheme circulated to settle disputes related to govt contracts

With respect to cases of ongoing litigation for disputes arising out of contracts in which physical activity has been stopped or contracts terminated, the settlement amount would be 30% of the net claim amount. For ongoing litigation where physica...

BCCL
For ongoing litigation where physical activity in the disputed contract is ongoing, the settlement amount would be 20% of the net claim amount -- claims by the contractors minus counter-claim by the procuring entity.
The finance ministry on Wednesday circulated a draft scheme for settlement of pending disputes related to government contracts. Under the 'Vivad se Vishwas II' (contractual disputes) scheme, contractors will be offered settlement amounts depending on the status of a dispute. In cases of disputes where court or arbitral order has been passed, the settlement amount will be 80% or 60% of the amount awarded by the court or the arbitral tribunal.

With respect to cases of ongoing litigation for disputes arising out of contracts in which physical activity has been stopped or contracts terminated, the settlement amount would be 30% of the net claim amount.

For ongoing litigation where physical activity in the disputed contract is ongoing, the settlement amount would be 20% of the net claim amount -- claims by the contractors minus counter-claim by the procuring entity.


In cases where the total claim amount exceeds ₹500 crore, the procuring entities will have an option not to accept the settlement request of the contractor, as per the draft scheme.

However, the reason will have to be recorded in the file by the procuring entities and has to be approved by the secretary of the concerned ministry/department or the CEO in case of a public sector enterprise.

For full report, go to
ADVERTISEMENT

www.economictimes.com

Download
The Economic Times Business News App
for the Latest News in Business, Sensex, Stock Market Updates & More.
Download
The Economic Times News App
for Quarterly Results, Latest News in ITR, Business, Share Market, Live Sensex News & More.
READ MORE
ADVERTISEMENT

READ MORE:

LOGIN & CLAIM

50 TIMESPOINTS

More from our Partners

Loading next story
Business News › News › Economy › Policy › Draft Scheme circulated to settle disputes related to govt contracts
Text Size:AAA
Success
This article has been saved

*

+