Noida’s new Sports City plan approved: Authority tells SC 70% of land will be reserved for sports facilities as stalled Sector 150 project moves towards revival
Noida Authority has approved the revised layout plan for the 300-acre Sports City project in Sector 150, reserving 70% of the land for sports facilities. The approval follows years of stalled development and comes as the Supreme Court examines sep...

Revised Sports City plan approved, Noida tells SC
Noida Sports City revised plan approved after public objections
In an affidavit submitted to the Supreme Court, Noida Authority said Lotus Greens Constructions submitted the revised layout plan, along with the prescribed fee, on January 2. The proposal received in-principle approval at the Authority's 222nd board meeting on April 6. Before that, public objections and suggestions were invited through newspaper advertisements and the Authority's website. The concerns received were subsequently addressed, following which formal approval was granted on May 6.Read more - New bigger Vande Bharat coming soon: Forget 16-coach version, Railways eyes 24-coach sleeper train with features that could give Rajdhani Express tough competition
The layout, prepared by Skyline Architectural Consultant and vetted by the Sports Authority of India (SAI), covers Plot 2 in Sector 150. The Authority also approved building plans for Plot SC-02 on June 9.
Four Sports City housing projects receive conditional occupancy certificates
Noida Authority has also issued conditional occupancy certificates for four housing projects developed by Brick Rise Developers, Ace Infracity, Land Kart Builders and Samridhi Infra Square.Read more - Less than 8% of India’s national highways are now narrower than two lanes: High-speed corridors grow 12 times as government plans 51,000 km of faster roads
The development is a separate step in the process of addressing pending approvals linked to the Sports City projects. The conditional nature of the certificates means the applicable requirements and conditions remain relevant.
For homebuyers who have waited years for progress, these approvals may be significant. However, the timelines for construction, completion and possession will depend on the status of individual projects and the clearances they require.
Revised plans submitted for other Noida Sports City projects
The process is also moving ahead for other projects in the area. Last month, Logix Infra Developers submitted a revised plan for Sector 150, 3C Green Developers submitted one for Sectors 78-79, and ATS Homes submitted a proposal for Sector 152.Noida Authority has invited public objections and suggestions on these proposals before taking further decisions. Their progress will depend on the review process and the steps required to secure approval.
On October 6, the Supreme Court decided to hear the cases concerning the three projects separately so that issues specific to each development could be examined. The next hearings are scheduled for December 9, December 16 and January 20.
Why was Noida Sports City development stalled?
The Sports City concept dates back to 2004, when Noida Authority planned sports infrastructure in connection with the Commonwealth Games. Four schemes were launched between 2010-11 and 2015-16, covering around 32.3 lakh square metres, or 798 acres. Under the schemes, 70% of the area was earmarked for sports facilities.The project later came under scrutiny after a Comptroller and Auditor General (CAG) report flagged irregularities, including allotments made without the required approvals.
On January 18, 2021, Noida Authority halted development-related processes, including building plan approvals and occupancy-related clearances. The CAG observations concerning Sports City were subsequently placed before the Uttar Pradesh Public Accounts Committee, which disposed of them on August 29, 2024.
What the Supreme Court's order means for homebuyers
On November 24, 2025, the Supreme Court directed Noida Authority to lift the development ban within 30-45 days. The revised layout approval is a step towards moving the project forward, but it does not mean every stalled development is now cleared for construction.The separate hearings will allow the court to examine the circumstances of individual projects. For homebuyers, the next key developments will be project-specific approvals, progress on construction and clarity on completion and possession timelines.
Inputs from TOI