Construction of Delhi-Mumbai Expressway will be completed by Oct, 2025: Gadkari
India's longest Greenfield Expressway, the Delhi-Mumbai Expressway, is slated for completion by October 2025. With 82 percent of the work completed as of June 2024, the project spans 1,386 km, connecting major economic centers. It is anticipated t...

"As of June 2024, a total 26 packages have been completed," Gadkari said.
According to him, the physical progress of the work is 82 per cent complete and a cumulative length of 1,136 km has been constructed.
"The revised scheduled completion date is October, 2025," he said.
The corridor provides connectivity to major economic centers within Delhi, Uttar Pradesh, Haryana, Rajasthan, Madhya Pradesh, Gujarat and Maharashtra.
As per the detailed project report (DPR), the impact includes reduction in distance from Delhi to Jawaharlal Nehru Port Trust (JNPT), in Mumbai by about 180 km and reduction in travel time of up to 50 per cent to the connected destinations.
Replying to a separate question, Gadkari said as on June 30, 2024, there are a total of 983 user fee plazas functional on National Highways.