Committed to develop infrastructure in North-East: NHIDCL

Hitting back at the Assam government, it said whatever delays were being caused in projects, were on account of delays in land acquisition, forest clearance etc by the state government.

Committed to develop infrastructure in North-East: NHIDCL
NEW DELHI: Terming its criticism by the Assam government as "unfortunate", state-run NHIDCL today said it is committed to "inclusive development" of the North-East region where it has already awarded projects worth Rs 4,008-crore in Assam with schemes worth another Rs 2,366-crore on anvil.

Hitting back at the Assam government, it said whatever delays were being caused in projects, were on account of delays in land acquisition, forest clearance etc by the state government.

"The criticism of NHIDCL by the state government of Assam is uncalled for, unfounded and unfortunate... the NHIDCL is committed to inclusive development of the North-East region and strategic border areas by becoming a catalyst for employment generation and economic growth," NHIDCL said.

The National Highways and Infrastructure Development Corporation Ltd (NHIDCL), created to fast-track highway projects, is a fully-owned company of the Ministry of Road Transport and Highways which had come under attack by Assam Chief Minister Tarun Gogoi earlier this month who said the pace of the projects by NHIDCL is slow.

"The fact is that NHIDCL, since its inception in July 2014, has been striving to enhance the pace of development of critical connectivity infrastructure in North-East... NHIDCL in the last one year has been able to fast-track activities for the construction of highways and development of other infrastructure in the North-East region and strategic border areas," it said.

"In Assam, the company has already awarded 10 projects covering a length of approximately 280 kms to be built with an estimated cost of Rs 4,008 crore.
ADVERTISEMENT

"The company would also be awarding 3 more projects in this state covering a length of approximately 102 kms to be built with an estimated cost of Rs 2,366 crore during the current financial year."

It said it has been able to fast-track the activities for construction of highways and other infrastructure in the state and has actually commenced work on Kaliabhoomra Bridge on NH 37A and Numaligarh-Jorhat section of NH 37.

"However, due to non receipt of estimates for land acquisition from the state government of Assam, slow progress of tree cutting and utility shifting to be done by the Assam government, all other projects are not able to move forward despite the contractors being put into place," the statement said.

It said it has raised the issue of delay in getting the estimates for land acquisition, forest clearance etc time and again at various levels, including in the meetings with Chief Minister and Chief Secretary.
ADVERTISEMENT

As the Assam government abruptly stopped collection of tolls on Kalia-Bhomora Bridge, NHIDCL had to quickly step in and bring in a contractor with revenues increasing by almost 36 per cent, it added.

It further said that since many road projects are held up due to delay in land acquisition, NHIDCL is now focusing on maintenance of roads in Assam, pending their upgradation.
ADVERTISEMENT

Road Transport and Highways Minister Nitin Gadkari had also held a meeting in Guwahati last month to fast-track projects in the region.
Download
The Economic Times Business News App
for the Latest News in Business, Sensex, Stock Market Updates & More.
Download
The Economic Times News App
for Quarterly Results, Latest News in ITR, Business, Share Market, Live Sensex News & More.
This vehicle will assess condition of highways in India
1/7
Dipak K Dash, TNN

In a major initiative to take stock of the condition of highways including their maintenance and next likely schedule for overlaying, the government is carrying out a road assessment exercise through a new modified vehicle.

We take a look at how this vehicle will gauge the health of highways:
Dipak K Dash, TNN

In a major initiative to take stock of the condition of highways including their maintenance and next likely schedule for overlaying, the government is carrying out a ..
Read More
This vehicle will collect data and other details for the new programme named road measurement and data acquisition system (RODMAS).

The vehicle has been imported from New Zealand.
This vehicle will collect data and other details for the new programme named road measurement and data acquisition system (RODMAS).

The vehicle has been imported from New Zealand.
The vehicle fitted with GPS, advanced lasers, automated measurement system, cameras to record HD videos will record road condition, wayside amenities, accident prone zones, road strength, condition of bridges and culverts besides encroachment.

All these data will be fed into a system to help government prioritize and plan maintenance, upgradation and expansion of certain stretches.
The vehicle fitted with GPS, advanced lasers, automated measurement system, cameras to record HD videos will record road condition, wayside amenities, accident prone zones, road strength, condition o..
Read More
The pilot exercise is being undertaken as a part of the World Bank project to provide technical assistance to NHAI.
The pilot exercise is being undertaken as a part of the World Bank project to provide technical assistance to NHAI.
Once the mechanism is set up and the institutional framework to maintain and manage the asset management system, more stretches will be covered.

The final target is to cover the entire 96,000 km of national highways.
Once the mechanism is set up and the institutional framework to maintain and manage the asset management system, more stretches will be covered.

The final target is to cover the entire 96,000..
Read More
While building new stretches and widening existing ones are seen as achievements for any ruling party, all these years governments have failed to keep the existing road network in good condition, something that often goes against the ruling establishment.

To start with about 3,000 km of highways spread across states including Uttar Pradesh, Gujarat, Madhya Pradesh, Maharashtra and Tamil Nadu will be covered by a vehicle equipped with modern gadgets to record every aspect of the road.
While building new stretches and widening existing ones are seen as achievements for any ruling party, all these years governments have failed to keep the existing road network in good condition, som..
Read More
During the pilot phase, surveys will be conducted thrice in a year. Such surveys should cover the entire NH network at least once in a year.

"This system will redefine our planning to undertake maintenance work on NHs, prepare work plan for expansion of priority stretches. We have already carried out some sort of similar exercise and the best technologies have been dovetailed for best assessment of the road asset," said Atul Kumar of NHAI, who is heading the project.
During the pilot phase, surveys will be conducted thrice in a year. Such surveys should cover the entire NH network at least once in a year.

"This system will redefine our planning to undertak..
Read More
READ MORE
ADVERTISEMENT

READ MORE:

LOGIN & CLAIM

50 TIMESPOINTS

More from our Partners

Loading next story
Business News › News › Economy › Infrastructure › Committed to develop infrastructure in North-East: NHIDCL
Text Size:AAA
Success
This article has been saved

*

+