Around 489 road projects face delays over land and clearance issues: Nitin Gadkari
Numerous road projects, initially slated for completion by March 2025, face delays due to land acquisition hurdles and pending clearances. The government is actively collaborating with states and stakeholders to resolve these issues. Cost overruns...

Union Road Transport and Highways Minister Nitin Gadkari, in a written reply to the Rajya Sabha, said the government is making all efforts to resolve the pending issues in close coordination with state governments and other stakeholders to complete these projects.
Gadkari said cost overrun has been incurred in some of the delayed projects due to various factors like enhanced cost of compensation for land and structures, price escalation, Goods & Services Tax (GST) impact, additional VUPs/PUPs on public demand or otherwise, change in General Arrangement Drawing (GAD)/design for Road Over Bridges/Road Under Bridges (ROBs/RUBs) to meet the Railway standards, etc.
If projects are inordinately delayed due to some reasons and further progress under the ongoing contract is not envisaged, the contract is terminated/foreclosed and re-awarded, with or without modification in the project configuration, he added.
Responding to a separate question, Gadkari said national highways are constructed in accordance with specifications of Indian Road Congress (IRC).
"The maximum design speed specified for construction of national highways in different terrains is 120 km/h for expressways and 100 km/h for national highways," he said.