566 national highway projects running behind schedule: Nitin Gadkari
In a separate reply, the minister said that to overcome the problem, "it has been now decided that projects are awarded only when 90 per cent of the land required is available and all the statutory clearances have been obtained".

The delays are mainly on account of issues in land acquisition and getting environment, forest and wildlife clearances, and disputes in arbitration, Road Transport and Highways Minister Nitin Gadkari said in a reply to a question in the Lok Sabha.
To fast-track these projects, various steps such as streamlining of land acquisition and environment clearances, premium re-scheduling, close coordination with other ministries, revamping of dispute resolution mechanism, frequent review meetings with project developers, state government and contractors at various levels have been taken, the minister said.
"Delay in completion leads to cost overrun in some projects," he said.
In a separate reply, the minister said that to overcome the problem, "it has been now decided that projects are awarded only when 90 per cent of the land required is available and all the statutory clearances have been obtained".