National Highway projects face cost overruns, delays as West Asia war disrupts supplies

India's National Highway projects are experiencing 5-8% cost increases and delays due to the West Asia war impacting input costs and supply chains. Key materials like bitumen, steel, and cement have seen significant price hikes, leading to project...

New Delhi: India's National Highway projects are facing 5-8% cost increases and delays as the West Asia war drives up input costs and disrupts supplies, sector executives said.

Companies are experiencing escalations in costs of key raw materials such as bitumen, steel, cement and fuel besides higher fuel costs and supply-chain disruptions due to ongoing geopolitical situations, executives of several companies engaged in the highways construction told ET.

National Highway Projects Face Cost Overruns, Delays
Input cost increases pegged at 5-8%; most players focus on strategic sourcing & long-term agreements

Taking control

"There have been intermittent delays and cost pressures with bitumen and fuel prices up by 25-20% while steel and electrical items have got costlier by 15-18%," said one of the executives who wished not to be identified. "Overall, these factors will have a marginal impact of up to 8% on project costs and, in many cases, timelines, depending on the project location and contract structure."


Most players are relying on strategic sourcing and long-term agreements with suppliers to keep the situation under control while those involved in the engineering, procurement and construction (EPC) projects are leveraging contractual clauses such as price escalation provisions where applicable.

Going forward, the focus would be on improving operational efficiencies, cost optimisation and diversifying supplier base to reduce dependency risks, an industry official said.

Cost mitigation

While the private sector is optimistic that early interventions by the government will ensure that the long-term infrastructure momentum is maintained, experts said the industry can look for alternatives to mitigate the cost escalation.
ADVERTISEMENT

"Contractors could undertake recycling of existing roads (recycled asphalt pavement) to bring the overall requirement down by 10-20% along with warm mix asphalt which will reduce the consumption of heating oil," said Phani Mandalaparthy, associate director at Crisil Intelligence.

Contractors are seen placing orders for loose bulk cement (through bulker trucks) rather than bags after a pan-India increase in prices of the per bag of cement, Mandalaparthy said.

The National Highways Builders Federation (NHBF) has requested extension of time (EoT), relief from penalties, compensation for extraordinary cost escalation, and a uniform approach across EPC, hybrid annuity model (HAM), and built-operate-transfer projects at a recent meeting with the National Highways Authority of India (NHAI). Feedback from project sites indicates increased transportation and logistics costs, higher operating expenses for construction plants, and working capital pressures,NHBF said
READ MORE
ADVERTISEMENT

READ MORE:

LOGIN & CLAIM

50 TIMESPOINTS

More from our Partners

Loading next story
Business News › Industry › Transportation › Roadways › National Highway projects face cost overruns, delays as West Asia war disrupts supplies
Text Size:AAA
Success
This article has been saved

*

+