Highway push: Centre races to slash project delays by March

India is accelerating its efforts to finalize numerous overdue highway initiatives by March, targeting a reduction in excess expenses and a faster pace of new road development. By hastening clearances and land acquisition, the government is paving...

India is racing to cut the backlog of long-delayed highway projects by March as it seeks to curb cost overruns and restore pace in national highway construction after project awards fell sharply this fiscal year.

Of the 152 delayed projects worth ₹71,500 crore as of April 2024, the road, transport and highways ministry has so far cleared 54. As of Monday, the count of delayed projects has declined to 98 projects worth ₹39,300 crore.

"The aim is to bring down the number of delayed projects to 60 by the end of the current financial year, which will be a 60% decline in pending projects in two years," a senior government official told ET.


image


Some of the targeted interventions include expediting project clearances, enabling swifter land procurement, and timely release of central funds so that construction could be put on fast-track, the official said.

"This will also help to arrest further escalation in cost of these projects due to delays," the official said.
ADVERTISEMENT

Project delays-a common occurrence in large infrastructure projects-often impacts cash flow and profitability at developers besides resulting in cost and time overruns.

National highway construction slowed in the first half of this fiscal as the ministry was focusing on streamlining processes to ensure quality and on-time construction.

The number of projects awarded but with work still to commence for more than a year has been reduced to 53 as of November at an estimated cost of ₹39,300 crore from 87 such projects worth ₹80,400 crore in April 2024.

The National Highways Authority of India, which constitutes roughly 45-50% of the country's national highway construction, has so far awarded 467.72 kms of highways, constructing 2108.38 kms. The figure sharply lagged the target of awarding 4,500 kms and constructing 5,000 km of highways in 2025-26.
ADVERTISEMENT

The official said the latest steps would help create a pipeline of projects as awards of new highways projects had slowed down considerably in the first half of FY26.

Projects are sometimes awarded but work is not initiated as the date of execution or the appointed date is not declared, which is often due to delays in fulfilling pre-construction requirements like land acquisition.
ADVERTISEMENT

Experts say the latest interventions will help increase the per day construction rate of highways.

"This will also benefit construction companies as they are currently burdened with significant overheads cost without commensurate construction revenues," said Kuljit Singh, national leader infrastructure, EY India.

Jagannarayan Padmanabhan, senior director & global head, consulting at Crisil Intelligence: "Clearing these stalled stretches frees up contractor capacity, improves lender confidence, and resets the project pipeline at a time when new awards have slowed."

He said this push is critical for meeting the remaining commitments under Bharatmala Phase I by 2026.
READ MORE
ADVERTISEMENT

READ MORE:

LOGIN & CLAIM

50 TIMESPOINTS

More from our Partners

Loading next story
Business News › Industry › Transportation › Roadways › Highway push: Centre races to slash project delays by March
Text Size:AAA
Success
This article has been saved

*

+