65-70% traffic could move off Delhi roads: First double-decker Metro-flyover reaches 88% completion, 1.4-km Yamuna Vihar-Bhajanpura stretch set for December 2026

Double-decker Metro-flyover
TOI-Online
1/7
Double-decker Metro-flyover
Delhi’s first integrated double-decker Metro-flyover is nearing completion, with 88% of construction work on the 1.4-km Karawal Nagar project now finished. The structure, being developed in northeast Delhi, will combine a flyover and Metro corridor on the same structure between Yamuna Vihar and Bhajanpura Metro stations.
Delhi double-decker Metro-flyover project reaches 88% completion
iStock
2/7
Delhi double-decker Metro-flyover project reaches 88% completion
The Delhi government has said construction of the Karawal Nagar double-decker project is 88% complete. The project is now targeted for completion by December 2026, with the revised cost estimate approved at Rs 291 crore. The structure is being developed to address traffic congestion on the busy stretch in northeast Delhi while accommodating the Metro corridor above the road.
Yamuna Vihar-Bhajanpura Metro corridor gets integrated structure
iStock
3/7
Yamuna Vihar-Bhajanpura Metro corridor gets integrated structure
The 1.4-km double-decker structure will run between Yamuna Vihar and Bhajanpura Metro stations, passing through Karawal Nagar, Ghonda and Brijpuri junction on Mangal Pandey Marg. The project is being executed by the Delhi Metro Rail Corporation (DMRC). An MoU between the Public Works Department (PWD) and DMRC for the project was signed on February 24, 2021.
Flyover and Metro corridor to run on the same structure
iStock
4/7
Flyover and Metro corridor to run on the same structure
Unlike conventional projects where road flyovers and Metro viaducts are built separately, the Karawal Nagar project integrates the two into a single double-decker structure. The arrangement is designed to make better use of the available space while providing an elevated route for both road traffic and Metro services. The project's original estimated cost was Rs 220 crore, which has since been revised to Rs 291 crore.
Karawal Nagar project faced delays over approvals
iStock
5/7
Karawal Nagar project faced delays over approvals
The project faced delays in 2023 after certain components could not proceed due to pending approvals. The Delhi government has now approved the revised project cost, with construction progressing towards the December 2026 completion target. With most of the civil work already completed, the project is expected to move closer to becoming operational once the remaining construction and associated works are finished.
65-70% traffic could shift to elevated route
iStock
6/7
65-70% traffic could shift to elevated route
The government expects the elevated structure to significantly ease congestion on the existing road. It estimates that around 65-70% of traffic could shift to the elevated route, leaving the surface road primarily for local traffic. The project is also expected to help create a signal-free stretch from Gokulpuri to Signature Bridge via Khajuri Khas, potentially reducing delays for commuters travelling through the congested northeast Delhi corridor.
December 2026 deadline for Delhi’s first double-decker Metro-flyover
iStock
7/7
December 2026 deadline for Delhi’s first double-decker Metro-flyover
The Karawal Nagar project is currently scheduled for completion by December 2026. Once completed, the 1.4-km structure will bring the road flyover and Metro corridor together in a single elevated structure between Yamuna Vihar and Bhajanpura. The project is being developed as Delhi’s first integrated double-decker Metro-flyover, with the government expecting it to improve traffic movement and provide an additional elevated transport corridor in northeast Delhi.