Surat Bullet Train Station First Images Out: Looks more like an airport than a railway station. Check out its stunning interiors

The first images of the under-construction Surat Bullet Train Station reveal its modern interiors, featuring geometric ceiling panels, glass railings and passenger amenities. The 50-km Surat-Bilimora section of the Mumbai-Ahmedabad high-speed rail...

The first images of the under-construction Surat Bullet Train Station offer a glimpse of its modern interiors, featuring geometric ceiling panels, glass railings, escalators and passenger facilities. The station is part of India's first bullet train project, with the 50-km Surat-Bilimora section of the Mumbai-Ahmedabad high-speed rail corridor being prepared for its initial trial run in May 2027.

First images of Surat Bullet Train Station

Surat-Bilimora section prepares for first trials

Railways Minister Ashwini Vaishnaw had earlier said that electrification work on the section had been completed, while signalling-related work was expected to be finished by January 2027.

The overhead electrification system on the elevated stretch was energised on November 20, covering both tracks. The section uses a 2x25 kV traction system, with installation work at the Bilimora traction substation also completed.


Vaishnaw said the high-speed rail corridor would be commissioned in phases rather than being opened in its entirety at once.

First images of Surat Bullet Train Station

Bullet train service to reach Thane by 2029

Under the proposed timeline, the Ahmedabad-Vapi section is expected to be completed by the end of 2027, while the service is targeted to reach Thane by 2029.

The initial testing will use the B-28 train, which has been designed to operate at speeds of up to 280 kmph.
ADVERTISEMENT

Explaining the engineering requirements of high-speed rail operations, Vaishnaw said trains travelling above 240 kmph require specialised design considerations. Pressure forces generated during movement must be factored into the engineering of both trains and supporting infrastructure.

First images of Surat Bullet Train Station

B-28 train clears pressure test

Vaishnaw said the B-28 train had successfully undergone a squeeze test, during which it was exposed to pressure levels twice the atmospheric pressure anticipated during actual operations.

The exercise was aimed at assessing the train's ability to withstand pressure-related challenges at high speeds.

The minister also expressed satisfaction over construction progress in Maharashtra, including work on the undersea tunnel, saying progress on these sections was encouraging.
ADVERTISEMENT

The Mumbai-Ahmedabad high-speed rail corridor is India's first bullet train project and is being developed to provide high-speed connectivity between the two major cities.

bullet-train
READ MORE
ADVERTISEMENT

READ MORE:

LOGIN & CLAIM

50 TIMESPOINTS

More from our Partners

Loading next story
Business News › Industry › Transportation › Railways › Surat Bullet Train Station First Images Out: Looks more like an airport than a railway station. Check out its stunning interiors
Text Size:AAA
Success
This article has been saved

*

+