Govt starts process of acquiring land worth over Rs 4,000 crore for second phase of Noida International Airport
The district is acquiring land from villages for Noida Airport's second phase. Resettlement and compensation are progressing. YIAPL plans test flights by November and aims for commercial operations by year's end. Completion delayed to April 2025. ...
For the said phase, the administration will be acquiring 1,365 acres of land. Out of the total land that will be obtained, nearly 1,181.3 hectares belongs to Karauli Bangar, Dayanatpur, Kuraib, Ranhera, Mudharh, and Beerampur villages. The entire acquisition will mount to Rs 4,898 crore.
The remaining land belongs to the government.
Status of project:
The administration has taken possession of 237 hectares of the 1,181 hectares earmarked for acquisition in six villages so far. Land has been acquired from three villages -- Birampur (54.6 out of 57.6 hectares), Dayantpur (145 out of 148 hectares), and Mudharh (37 out of 48 hectares), reported ToI.
“The process of taking possession in the remaining villages is underway. The compensation distribution is in its final stage. We are taking possession of the land where all the processes have been completed,” said district magistrate Manish Kumar Verma.
Back in 2022, the Yogi Adityanath-led government had issued a notification to acquire land for the second phase, and the distribution of compensation for the same began in July last year.
Additionally, the resettlement and rehabilitation (R&R) process is in progress to relocate farmers from three villages.
Approximately 13,000 families affected by land acquisition for the second phase will be resettled in Falaida Bangar and Modalpur, requiring 212 hectares of land. Farmers from Ranhera, Kuraib, and Karoli Bangar villages will be completely displaced.
Meanwhile, officials from the Noida International Airport Limited (NIAL), which is overseeing the airport project, said that private concessionaire Yamuna International Airport Ltd (YIAPL) is in talks with the DGCA and Airport Authority of India to start test flights by November this year as the full operations are slated to begin by end of this year.
During an inspection on June 28, then-chief secretary DS Mishra instructed the concessionaire to start commercial services by Dec at any cost and requested the developer to submit an action plan for the same by July 15.
The CEO went on to say that necessary equipment, including the instrument landing system (CAT 1 and CAT 3), will be installed before test flights begin.