NHAI cancels 2 Essar contracts
Highlights
The two projects were expected to be completed by August 2004. However, the present status indicates only about 70% project completion. Inspite of several warnings and meetings with the minister of shipping, road transport and highways, Essar has failed to pull up its socks.
���Essar was given enough opportunities to speed up the pace of work, but the performance has been unsatisfactory. First, the independent engineer of the projects issued them a notice. Now, we have also taken action,��� NHAI chairman Pradeep Kumar told ET.
However, Essar officials declined to comment. ���This is a matter between the contractor and employer. We would not like to comment,��� an Essar spokesperson said. The two ADB-funded contracts were for the 75-km Chitradurga-Harihar stretch and 56-km long Harihar-Haveri project, both on NH-4.
The status as on December 31, 2006 was 71% and 69% project completion for the two stretches, respectively. Both the terminated highway projects were being
developed by a joint venture of Essar with Malaysian contractor UEM.
The move will delay the project. NHAI will now have to re-award the two contracts. This process could take up to a year, NHAI spokesperson said. The GQ project, or phase I of the National Highways Development Programme, is expected to be completed by December 2008. About 95% of GQ has been completed so far.
The Economic Times News App for Quarterly Results, Latest News in ITR, Business, Share Market, Live Sensex News & More.