Delay in approvals not covered under force majeure, says Bombay HC, rules in favour of homeowners
The court has dismissed realty developer Westin Developers’ appeal against a Real Estate Regulatory Authority’s (RERA) order to set aside a six-month grace period allowed earlier.
The court has dismissed realty developer Westin Developers’ appeal against a Real Estate Regulatory Authority’s (RERA) order to set aside a six-month grace period allowed earlier.
“Developers now cannot rely on usual majeure clauses in flat agreements to deny interest under RERA for delayed possession of flat as contractually agreed,” said Huzefa Nasikwala, founding partner of Nasikwala Law Office, who represented the respondent in the case.
The RERA Appellate Tribunal had also directed the developer to pay interest to the homebuyer from the scheduled date of delivery until the actual possession.
In this particular case, the developer, through a second appeal, had challenged an order passed by RERA Appellate Tribunal, Mumbai following a homebuyer’s complaint of delay in handing over the apartment.
The homebuyer had also claimed interest from the developer as compensation for the delay from the scheduled delivery date and actual possession.
The adjudicating authority under Maharashtra Real Estate (Regulation and Development) Act, 2016, while accepting the homebuyer’s claim, had awarded interest from January 2018 along with six-months extension to the developer as grace period.

When the matter was pursued before the RERA Appellate Tribunal, it held that there was no specific clause in the agreement, entitling the developer to any grace period of six months or otherwise.
The tribunal observed that the date of delivery of possession of the premises stipulated under the agreement, was on or before June 30, 2017 and, accordingly, directed payment of interest from July 1, 2017 till the date of delivery of possession.
According to the latest ruling, this clause is nothing but an ordinary force majeure clause where the promoter cannot be faulted for delay in delivery of possession, if such delay is caused by any reason beyond his control. And this clause by itself does not provide for any grace period to the promoter.
It is important to note that neither the Appellate Tribunal nor the adjudicating authority found justification for the delay.
The grace period of six months considered by the adjudicating authority was nothing but an ad-hoc measure and was rightly not accepted by the Appellate Tribunal, the court said while dismissing the developer’s appeal.
The Economic Times News App for Quarterly Results, Latest News in ITR, Business, Share Market, Live Sensex News & More.