Less paperwork, fixed timelines to make solar rooftop installations simpler in Delhi
Delhi has simplified rooftop solar regulations to encourage domestic adoption. The process now involves two steps, reducing paperwork and eliminating registration fees. Technical feasibility analysis is waived for systems up to 10 kW capacity. Dis...
Under the amended Delhi Electricity Regulatory Commission (Net Metering for Renewable Energy) Regulations, 2014, the existing three-stage application and registration process has been replaced with a two-step process.
Also Read: India's installed solar capacity rises 57-fold since 2014 to 162.15 GW, Government tells Parliament
Previously, the three-tier process involved feasibility analysis, registration and a connection agreement. Now, the technical feasibility stage will be followed by an integrated document verification, inspection and net meter installation stage, with no registration fees.
Domestic consumers may apply through the PM Surya Ghar portal for rooftop solar connection if they seek subsidy under the PM Surya Ghar: Muft Bijli Yojana.
Also Read: China's world-leading renewable megabases rely on coal-heavy transmission
As per the amended regulations, the discoms will complete the technical feasibility analysis within 15 days. After application and upon their failure to conduct the analysis within the given time, it will be deemed to have been granted.
Importantly, no technical feasibility analysis will be required for rooftop systems of capacity up to 10 kW.
No feasibility analysis or registration fee will be payable to domestic consumers for rooftop solar connections up to 10 kW, irrespective of whether or not such consumers avail benefits under the PM Surya Ghar: Muft Bijli Yojana.