India lets clean-energy projects pay to keep grid access after delays

India's power regulator allows clean energy firms to pay for extended grid access. Developers can secure extra time by paying daily fees per megawatt. This change helps projects delayed by land and financing issues. Companies receive up to twel...

New Delhi: India's power regulator has allowed clean energy developers to pay more to keep their grid connectivity after missing project deadlines, instead of losing their access to the transmission network.

Also Read: ITA backs 11 Indian projects; to advance over $18 bn in clean industry investment

Here are some details:


* Power producers can get extra time ‌instead of automatically ⁠losing ⁠their grid connectivity rights, the Central Electricity Regulatory Commission said in an order over the weekend.

* Producers will have to pay 1,000 ​Indian rupees ($10.48) per megawatt per day to obtain extra time for land and financing requirements and 3,000 rupees per ​MW per day for delays ⁠in starting commercial ‌operations.

* The move comes after several ​companies approached ​the regulator seeking more time for projects ⁠that were delayed but still under development as ​India's grid planning authority started serving disconnection notices.
ADVERTISEMENT

Also Read: India's clean energy push must shift from capacity to adoption: Experts

* ​Grid connectivity is a limited resource and projects holding grid capacity without making progress can prevent others from using it, the regulator said.

* Several clean energy projects have been stalled in India because of a ‌lack of transmission infrastructure.

* Companies can get up to three additional months to complete land ​requirements, six ​months to ⁠secure financing and as much as 12 months to commission projects, the regulator said.
ADVERTISEMENT

* Those that still fail to meet ​the deadlines risk losing their grid connectivity and associated bank guarantees.

* India is looking to add about 500 gigawatts of non-fossil fuel based power from about 300 GW at present.
READ MORE
ADVERTISEMENT

READ MORE:

LOGIN & CLAIM

50 TIMESPOINTS

More from our Partners

Loading next story
Business News › Industry › Renewables › India lets clean-energy projects pay to keep grid access after delays
Text Size:AAA
Success
This article has been saved

*

+