Crompton bags 3.5 mn euros onshore project in France
The scope of the work includes design, engineering, supply, installation and commissioning of the substation.
The scope of the work includes design, engineering, supply, installation and commissioning of the substation. CG (Crompton Greaves) will also be responsible for upgrading and building the overall electrical system, it said in a statement.
The company will have to supply two 45 MVA step-up power transformers, medium and high voltage air insulated switchgear (AIS), substation automation system (SAS), buildings and ancillaries.
"The substation will help to integrate wind energy and boost power supplies to meet the growing residential demand besides reinforcing the transmission grid and improving reliability, efficiency and power quality," the company said.
The project is scheduled for completion by mid 2014. "This win demonstrates CG's local project management strengths and on and offshore track record besides our cost-efficient approach in offering turnkey grid infrastructure solutions," company's CEO and Managing Director Laurent Demortier said.
The Economic Times News App for Quarterly Results, Latest News in ITR, Business, Share Market, Live Sensex News & More.