Ceigall India receives LOI for Rs 5,300-cr transmission project in Gujarat
Ceigall India has received a letter of intent for a major transmission system project. This project, valued at Rs 5,300 crore, will be developed in Gujarat. It involves building a substation and transmission lines to evacuate renewable energy. ...
The LoI has been awarded for the 'Common Transmission System for evacuation of power from Lakadia (Phase-II: 7.5 GW), Jam Khambhaliya (Phase-II: 5.5 GW) and Jamnagar (Phase-I: 1 GW) - Part-B' project, a company statement said.
The project entails the development of a 765/400 kV Air Insulated Substation (AIS) along with approximately 300 km of transmission lines.
The project is valued at approximately Rs 5,300 crore (inclusive of GST).
The company will receive annual transmission charges of Rs 608.67 crore each year over the 35-year operational period.
Execution is expected to take 36 months, followed by this 35-year operational period.
The project forms part of the transmission infrastructure being developed to facilitate the evacuation of power from key renewable energy zones in Gujarat, including Lakadia, Jam Khambhaliya and Jamnagar.
"The project will contribute to the development of critical power transmission infrastructure in Gujarat and support the efficient evacuation of power from key generation regions," said Ramneek Sehgal, Managing Director, Ceigall India Ltd.