Sikkim landslide caused Rs 327 cr loss to Teesta-V project: NHPC
NHPC's 510 MW Teesta-V Power Station in Sikkim has been severely affected by a major landslide. The estimated loss is around Rs 327.67 crore. Currently, the power station is not operational and is undergoing restoration works after the flash flood...
The "estimated total amount of loss/ Re-do cost towards material damage (being intimated to insurance company) due to landslide at Teesta-V Power Station (510 MW) occurred on August 20, 2024 is Rs.327.67 crore."
Teesta-V Power Station (3x170 MW) is a run of the river scheme with diurnal storage to harness the hydro power potential of river Teesta for peaking during the lean season and is located in the state of Sikkim.
The power station was commissioned in 2008.