NALCO commissions second wind power unit in Jaisalmer
NALCO commissioned its second wind power plant at Ludarva in Jaisalmer district of Rajasthan last week, with a capacity of 47.6 MW.
In the first phase of commissioning, 36 turbines were erected. The remaining 20 turbines were successfully commissioned last week. In a statement, Nalco said it the company's second green initiative towards promoting sustainable development by harnessing the unconventional and renewable energy sources, which would credit the company with incentives from the government.
Earlier, the company commissioned its first wind power plant of 50.4 MW capacity at a cost of Rs 274 crore at Gandikota in Kadapa district of Andhra Pradesh, in December, 2012. The company is now planning to set up a third wind power plant in its own mined out area of Panchpatmali bauxite deposit in Odisha'a Koraput.