L&T bags 'significant' electrification order for Mumbai Metro railway project
Larsen & Toubro has secured a significant order for the Mumbai Metro Line 4 electrification project. The contract involves design, supply, installation, and commissioning of power and traction systems. L&T will also handle electrical and mechanica...
L&T classifies an order amount ranging between Rs 1,000 cr to Rs 2,500 cr as 'significant'.
Also read: L&T onshore vertical bags 'major' order from BPCL to build India's largest flexible petrochemical plant
Under the order, L&T will electrify 24.72 km long metro line 4 that runs between Bhakti Park (Wadala) to Cadbury junction with 22 elevated stations.
The scope of order includes design, manufacture, supply, installation, integration, testing and commissioning of power supply and traction systems for 24.72 route km and provision of SCADA system for complete Metro line 4 & 4A for 32 stations, depots and receiving substation, the company said in a regulatory filing.
L&T has also received the order for electrical and mechanical works, lift & escalators for 22 elevated stations and 2 Depots, along with five years of comprehensive maintenance.
Mumbai Metro earlier appointed L&T for Package CA-234, involving rolling stock, Communications-Based Train Control (CBTC) signalling, telecommunications, platform screen doors and depot machinery & plant for the entire corridor, and gave another order for Package CA-168, involving 19.5 km ballast-less track-works across 15 stations.