According to the statement, under International Competitive Bidding (ICB), Bharat Heavy Electricals Ltd (BHEL) has bagged an order from NTPC for setting up the 2x800 MW Singrauli Supercritical Thermal Power Plant (STPP) Stage-III on Engineering, P...
Set up by BHEL in 1982, Singrauli TPS was NTPC's first power plant in the state.
The machines installed earlier by BHEL at Singrauli have been performing exceedingly well since commissioning, it said.
According to the statement, under International Competitive Bidding (ICB), Bharat Heavy Electricals Ltd (BHEL) has bagged an order from NTPC for setting up the 2x800 MW Singrauli Supercritical Thermal Power Plant (STPP) Stage-III on Engineering, Procurement & Construction (EPC) basis.
Key equipment for the project will be supplied by BHEL's manufacturing units at Haridwar, Trichy, Bengaluru, Hyderabad, Ranipet, and Bhopal.