Adani Power starts supplying power to Bangladesh from its Jharkhand plant
In a regulator filing on Monday, the company said Unit 2 of 800 MW capacity of its 2x800 MW ultra-supercritical power project of its wholly-owned subsidiary Adani Power (Jharkhand) Ltd (APJL) has achieved commercial operations at 24:00 hrs Banglad...
"Accordingly, APJL will export (w.e.f. 00.00 hrs Bangladesh time, of June 26, 2023), entire power generated from the 2x800 MW Godda plant on commercial basis, as per Power Purchase Agreement, directly to Bangladesh through the dedicated 400 kV transmission lines, with net capacity of 1,496 MW," it said.
The plant is located in Godda district in Jharkhand. APJL has a 25-year contract with Bangladesh Power Development Board (BPDB).