Coal stock at power plants improve
According to CEA data, there are a few coal plants with one-three days stock but they are not deemed critical as they are either close to a mine or have consumed most of their coal quota.
From the time when some plants ran out of fuel, the only one with critical stocks now is GMR’s Warora plant, which has enough coal to run for four days.
A senior Coal India executive said the plant was running at more than 90% capacity, and that stocks were down because of logistical issues. “Two rakes are being sent every day and they are managing,” he said.
According to CEA data, there are a few coal plants with one-three days stock but they are not deemed critical as they are either close to a mine or have consumed most of their coal quota.